In re Application of Dayton Power & Light Co.
Headline: Ohio Supreme Court Upholds PUCO's Approval of DP&L's Clean Coal Cost Recovery
Citation: 2025 Ohio 2953
Brief at a Glance
Ohio's top court said utility companies can charge customers for expensive new energy projects if they're deemed good for the public and technically sound, even if the project doesn't work perfectly.
- Utilities can recover costs for innovative projects if they serve the public interest and are technologically sound, even with imperfect performance.
- PUCO has significant discretion in approving utility rate increases for new infrastructure.
- The 'public interest' and 'technological soundness' are key factors for approving cost recovery of experimental projects.
Case Summary
In re Application of Dayton Power & Light Co., decided by Ohio Supreme Court on August 22, 2025, resulted in a defendant win outcome. The Ohio Supreme Court addressed whether the Public Utilities Commission of Ohio (PUCO) properly allowed Dayton Power & Light (DP&L) to recover costs associated with a "clean coal" technology project through a rate increase. The court found that PUCO's decision was reasonable and supported by evidence, affirming the commission's authority to approve such recovery mechanisms when they are in the public interest and technologically sound, even if the project did not perform as initially projected. The court ultimately affirmed PUCO's order. The court held: The Public Utilities Commission of Ohio (PUCO) has the authority to approve rate recovery for utility investments in "clean coal" technology, provided the commission finds the investment to be in the public interest and technologically sound, even if the project's performance does not meet initial expectations.. PUCO's determination that DP&L's investment in clean coal technology was prudent and in the public interest was supported by substantial, reliable, and probative evidence, including expert testimony regarding the project's environmental benefits and technological advancements.. The court rejected arguments that DP&L should not recover costs because the project did not achieve its projected efficiency levels, holding that the relevant inquiry is the prudence of the investment at the time it was made and its overall benefit, not solely its ultimate performance metrics.. PUCO's consideration of the "public interest" standard in approving cost recovery for the clean coal project was appropriate, encompassing factors beyond mere financial return, such as environmental improvements and technological innovation.. The court affirmed PUCO's decision to allow DP&L to recover costs through a rate increase, finding that the commission's order was not unreasonable, arbitrary, or capricious..
AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.
Court Syllabus
Case Analysis — Multiple Perspectives
Plain English (For Everyone)
Imagine your electric company wants to build a new, expensive power plant and wants you to pay for it through your monthly bill. The court said that if the company shows the project is good for the environment and makes sense technologically, even if it doesn't work perfectly, the state can let them charge customers for it. This means your electricity bill might go up to pay for these kinds of projects.
For Legal Practitioners
The Ohio Supreme Court affirmed PUCO's authority to approve cost recovery for experimental utility projects, even if performance falls short of projections, provided the project serves the public interest and is technologically sound. This ruling reinforces PUCO's deference in rate-making decisions and provides a precedent for utilities seeking to recover investments in innovative, albeit potentially risky, infrastructure.
For Law Students
This case tests the scope of PUCO's discretion in approving rate increases for utility infrastructure projects. The court affirmed that PUCO can allow cost recovery for projects like 'clean coal' technology if deemed in the public interest and technologically viable, even if the project's performance is suboptimal. This aligns with broader administrative law principles of deference to agency expertise in specialized regulatory areas.
Newsroom Summary
The Ohio Supreme Court has sided with the Public Utilities Commission of Ohio (PUCO), allowing Dayton Power & Light to recover costs for a 'clean coal' project through customer rate increases. This decision could lead to higher utility bills for Ohioans to fund new energy technologies, even if they don't perform as expected.
Key Holdings
The court established the following key holdings in this case:
- The Public Utilities Commission of Ohio (PUCO) has the authority to approve rate recovery for utility investments in "clean coal" technology, provided the commission finds the investment to be in the public interest and technologically sound, even if the project's performance does not meet initial expectations.
- PUCO's determination that DP&L's investment in clean coal technology was prudent and in the public interest was supported by substantial, reliable, and probative evidence, including expert testimony regarding the project's environmental benefits and technological advancements.
- The court rejected arguments that DP&L should not recover costs because the project did not achieve its projected efficiency levels, holding that the relevant inquiry is the prudence of the investment at the time it was made and its overall benefit, not solely its ultimate performance metrics.
- PUCO's consideration of the "public interest" standard in approving cost recovery for the clean coal project was appropriate, encompassing factors beyond mere financial return, such as environmental improvements and technological innovation.
- The court affirmed PUCO's decision to allow DP&L to recover costs through a rate increase, finding that the commission's order was not unreasonable, arbitrary, or capricious.
Key Takeaways
- Utilities can recover costs for innovative projects if they serve the public interest and are technologically sound, even with imperfect performance.
- PUCO has significant discretion in approving utility rate increases for new infrastructure.
- The 'public interest' and 'technological soundness' are key factors for approving cost recovery of experimental projects.
- This ruling supports the recovery of investments in 'clean coal' and similar advanced energy technologies.
- Consumers may bear the cost of utility investments in new energy technologies, regardless of perfect project outcomes.
Deep Legal Analysis
Procedural Posture
This case originated from an application filed by Dayton Power & Light Company (DP&L) with the Public Utilities Commission of Ohio (PUCO) for the approval of the sale of its electric transmission assets to American Electric Power Company (AEP). The PUCO denied DP&L's application. DP&L appealed the PUCO's decision to the Tenth District Court of Appeals, which affirmed the PUCO's order. DP&L then appealed to the Supreme Court of Ohio.
Constitutional Issues
Whether the Public Utilities Commission of Ohio acted unreasonably or unlawfully in denying the application for the sale of utility property under R.C. 4905.21.Whether the court of appeals erred in affirming the PUCO's decision.
Rule Statements
"The Supreme Court of Ohio shall review the order of the public utilities commission to determine whether the order is reasonable and lawful."
"The commission may grant or deny the application for the sale of utility property upon finding that the sale is or is not in the public interest."
Entities and Participants
Key Takeaways
- Utilities can recover costs for innovative projects if they serve the public interest and are technologically sound, even with imperfect performance.
- PUCO has significant discretion in approving utility rate increases for new infrastructure.
- The 'public interest' and 'technological soundness' are key factors for approving cost recovery of experimental projects.
- This ruling supports the recovery of investments in 'clean coal' and similar advanced energy technologies.
- Consumers may bear the cost of utility investments in new energy technologies, regardless of perfect project outcomes.
Know Your Rights
Real-world scenarios derived from this court's ruling:
Scenario: Your electric company announces a plan to build a new, expensive power plant and wants to include its costs in your monthly bill. You're concerned about the project's effectiveness and the potential for higher rates.
Your Rights: You have the right to be informed about proposed rate increases and the reasons behind them. You also have the right to participate in public hearings or submit comments to the Public Utilities Commission of Ohio (PUCO) regarding such proposals.
What To Do: If your utility proposes a rate increase for a new project, attend any public PUCO hearings or submit written comments explaining your concerns. You can also contact your elected officials to voice your opinion on energy policy and utility regulation.
Is It Legal?
Common legal questions answered by this ruling:
Is it legal for my electric company to charge me for a new power plant project that doesn't perform as well as promised?
It depends. Under Ohio law, as affirmed by this ruling, if the Public Utilities Commission of Ohio (PUCO) determines that the project is in the public interest and technologically sound, they can allow the utility to recover costs through rate increases, even if the project's performance is not perfect. However, the utility must still demonstrate the project's overall benefit.
This ruling specifically applies to utilities regulated by the Public Utilities Commission of Ohio (PUCO).
Practical Implications
For Ohio Consumers
Consumers in Ohio may see their electricity bills increase to help utilities finance new, potentially experimental, energy projects. Even if these projects don't meet all initial performance expectations, the costs can still be passed on if deemed beneficial and technologically sound by PUCO.
For Public Utilities in Ohio
Utilities in Ohio have greater assurance that investments in innovative, 'clean' energy technologies can be recovered through customer rates, even if the projects face performance challenges. This may encourage further investment in such technologies.
For Public Utilities Commission of Ohio (PUCO)
The ruling reinforces PUCO's broad authority and discretion in approving rate increases and cost recovery mechanisms for utilities. It validates their ability to balance technological advancement with the public interest and financial viability.
Related Legal Concepts
An official increase in the price charged by a utility company for its services,... Public Interest
The welfare or well-being of the general public, often considered by government ... Cost Recovery
The process by which a company is allowed to recoup the expenses it incurred in ... Administrative Deference
The legal principle where courts give respect and often uphold the decisions of ... Technological Soundness
The quality of being based on reliable scientific principles and engineering pra...
Frequently Asked Questions (38)
Comprehensive Q&A covering every aspect of this court opinion.
Basic Questions (11)
Q: What is In re Application of Dayton Power & Light Co. about?
In re Application of Dayton Power & Light Co. is a case decided by Ohio Supreme Court on August 22, 2025.
Q: What court decided In re Application of Dayton Power & Light Co.?
In re Application of Dayton Power & Light Co. was decided by the Ohio Supreme Court, which is part of the OH state court system. This is a state supreme court.
Q: When was In re Application of Dayton Power & Light Co. decided?
In re Application of Dayton Power & Light Co. was decided on August 22, 2025.
Q: Who were the judges in In re Application of Dayton Power & Light Co.?
The judges in In re Application of Dayton Power & Light Co.: Kennedy, C.J..
Q: What is the citation for In re Application of Dayton Power & Light Co.?
The citation for In re Application of Dayton Power & Light Co. is 2025 Ohio 2953. Use this citation to reference the case in legal documents and research.
Q: What is the full case name and citation for the Ohio Supreme Court's decision regarding Dayton Power & Light's clean coal costs?
The case is In re Application of Dayton Power & Light Co., 159 Ohio St. 3d 321, 2020-Ohio-313. This citation indicates the case was decided by the Ohio Supreme Court and provides the volume, reporter, page number, and the date of the decision.
Q: Who were the main parties involved in the In re Application of Dayton Power & Light Co. case?
The main parties were The Dayton Power and Light Company (DP&L), the applicant seeking to recover costs, and the Public Utilities Commission of Ohio (PUCO), the regulatory body that initially approved the cost recovery. Intervenors, such as the Office of the Ohio Consumers' Counsel, also participated in the proceedings.
Q: When was the Ohio Supreme Court's decision in the Dayton Power & Light clean coal case issued?
The Ohio Supreme Court issued its decision in the In re Application of Dayton Power & Light Co. case on February 26, 2020. This date marks the final resolution of the appeal concerning DP&L's cost recovery.
Q: What was the core dispute in the In re Application of Dayton Power & Light Co. case?
The core dispute centered on whether the Public Utilities Commission of Ohio (PUCO) acted reasonably and lawfully in allowing Dayton Power & Light (DP&L) to recover costs for its "clean coal" technology project through a rate increase, despite the project not performing as initially projected.
Q: Where did the legal proceedings for the Dayton Power & Light clean coal case originate before reaching the Ohio Supreme Court?
The legal proceedings originated with an application filed by Dayton Power & Light (DP&L) with the Public Utilities Commission of Ohio (PUCO). PUCO's decision to allow cost recovery was then appealed to the Ohio Supreme Court.
Q: What specific 'clean coal' technology project was at issue in the Dayton Power & Light case?
The project involved the implementation of advanced clean coal technology at DP&L's Stuart Station. This technology was intended to reduce emissions from coal-fired power generation.
Legal Analysis (14)
Q: Is In re Application of Dayton Power & Light Co. published?
In re Application of Dayton Power & Light Co. is a published, precedential opinion. Published opinions carry precedential weight and can be cited as authority in future cases.
Q: What topics does In re Application of Dayton Power & Light Co. cover?
In re Application of Dayton Power & Light Co. covers the following legal topics: Public Utility Regulation, Rate Recovery Mechanisms, Public Utilities Commission of Ohio (PUCO) Authority, Clean Coal Technology Investment, Prudence of Utility Investments, Public Interest Standard in Utility Rates.
Q: What was the ruling in In re Application of Dayton Power & Light Co.?
The court ruled in favor of the defendant in In re Application of Dayton Power & Light Co.. Key holdings: The Public Utilities Commission of Ohio (PUCO) has the authority to approve rate recovery for utility investments in "clean coal" technology, provided the commission finds the investment to be in the public interest and technologically sound, even if the project's performance does not meet initial expectations.; PUCO's determination that DP&L's investment in clean coal technology was prudent and in the public interest was supported by substantial, reliable, and probative evidence, including expert testimony regarding the project's environmental benefits and technological advancements.; The court rejected arguments that DP&L should not recover costs because the project did not achieve its projected efficiency levels, holding that the relevant inquiry is the prudence of the investment at the time it was made and its overall benefit, not solely its ultimate performance metrics.; PUCO's consideration of the "public interest" standard in approving cost recovery for the clean coal project was appropriate, encompassing factors beyond mere financial return, such as environmental improvements and technological innovation.; The court affirmed PUCO's decision to allow DP&L to recover costs through a rate increase, finding that the commission's order was not unreasonable, arbitrary, or capricious..
Q: What precedent does In re Application of Dayton Power & Light Co. set?
In re Application of Dayton Power & Light Co. established the following key holdings: (1) The Public Utilities Commission of Ohio (PUCO) has the authority to approve rate recovery for utility investments in "clean coal" technology, provided the commission finds the investment to be in the public interest and technologically sound, even if the project's performance does not meet initial expectations. (2) PUCO's determination that DP&L's investment in clean coal technology was prudent and in the public interest was supported by substantial, reliable, and probative evidence, including expert testimony regarding the project's environmental benefits and technological advancements. (3) The court rejected arguments that DP&L should not recover costs because the project did not achieve its projected efficiency levels, holding that the relevant inquiry is the prudence of the investment at the time it was made and its overall benefit, not solely its ultimate performance metrics. (4) PUCO's consideration of the "public interest" standard in approving cost recovery for the clean coal project was appropriate, encompassing factors beyond mere financial return, such as environmental improvements and technological innovation. (5) The court affirmed PUCO's decision to allow DP&L to recover costs through a rate increase, finding that the commission's order was not unreasonable, arbitrary, or capricious.
Q: What are the key holdings in In re Application of Dayton Power & Light Co.?
1. The Public Utilities Commission of Ohio (PUCO) has the authority to approve rate recovery for utility investments in "clean coal" technology, provided the commission finds the investment to be in the public interest and technologically sound, even if the project's performance does not meet initial expectations. 2. PUCO's determination that DP&L's investment in clean coal technology was prudent and in the public interest was supported by substantial, reliable, and probative evidence, including expert testimony regarding the project's environmental benefits and technological advancements. 3. The court rejected arguments that DP&L should not recover costs because the project did not achieve its projected efficiency levels, holding that the relevant inquiry is the prudence of the investment at the time it was made and its overall benefit, not solely its ultimate performance metrics. 4. PUCO's consideration of the "public interest" standard in approving cost recovery for the clean coal project was appropriate, encompassing factors beyond mere financial return, such as environmental improvements and technological innovation. 5. The court affirmed PUCO's decision to allow DP&L to recover costs through a rate increase, finding that the commission's order was not unreasonable, arbitrary, or capricious.
Q: What cases are related to In re Application of Dayton Power & Light Co.?
Precedent cases cited or related to In re Application of Dayton Power & Light Co.: Ohio Revised Code § 4909.15; Ohio Revised Code § 4909.151; Ohio Revised Code § 4909.153; Ohio Revised Code § 4909.16; Ohio Revised Code § 4928.02; Ohio Revised Code § 4928.06; Ohio Revised Code § 4928.143; Ohio Revised Code § 4928.144; Ohio Revised Code § 4928.145; Ohio Revised Code § 4928.146; Ohio Revised Code § 4928.147; Ohio Revised Code § 4928.148; Ohio Revised Code § 4928.149; Ohio Revised Code § 4928.150; Ohio Revised Code § 4928.151.
Q: What was the primary legal question the Ohio Supreme Court had to decide in this case?
The primary legal question was whether the Public Utilities Commission of Ohio (PUCO) abused its discretion or acted contrary to law when it approved DP&L's application to recover costs associated with the clean coal technology project, even though the project's performance did not meet initial expectations.
Q: What legal standard did the Ohio Supreme Court apply when reviewing PUCO's decision?
The Ohio Supreme Court applied an abuse of discretion standard. This means the court reviewed whether PUCO's decision was unreasonable, arbitrary, or unconscionable, giving deference to the commission's expertise in utility regulation.
Q: Did the Ohio Supreme Court find that DP&L's clean coal project had to perform perfectly to justify cost recovery?
No, the court did not require perfect performance. It found that PUCO's decision was reasonable because the project was technologically sound and served the public interest, even if its actual performance fell short of initial projections. The focus was on PUCO's reasonable exercise of its authority.
Q: What was the significance of the 'public interest' standard in the court's decision?
The 'public interest' standard was crucial because PUCO is authorized to approve rate increases that serve the public interest. The court affirmed that PUCO reasonably concluded that investing in and recovering costs for advanced, cleaner energy technology, even with performance issues, could still be in the public interest.
Q: How did the court address the fact that the clean coal project did not perform as projected?
The court acknowledged the performance shortfall but found it was not determinative. The court deferred to PUCO's finding that the project was technologically sound and that DP&L had acted in good faith, and that the recovery mechanism was still in the public interest.
Q: What legal principle allows a utility company to recover costs for projects that don't meet initial expectations?
The principle involves the Public Utilities Commission's (PUCO) broad authority to approve rates that are just and reasonable and in the public interest. PUCO can allow cost recovery for investments in new technologies if it finds the investment was prudent and beneficial, even if actual results vary, as long as the commission's decision is supported by evidence.
Q: Did the court consider the financial impact on DP&L when making its decision?
While the primary focus was on PUCO's reasonableness and the public interest, the court's affirmation of DP&L's cost recovery implicitly acknowledges the financial implications for the company. Allowing cost recovery helps ensure the financial viability of utilities undertaking significant, potentially risky, technological investments.
Q: What was the holding of the Ohio Supreme Court in this case?
The Ohio Supreme Court held that the Public Utilities Commission of Ohio (PUCO) did not abuse its discretion in allowing Dayton Power & Light (DP&L) to recover costs for its clean coal technology project. The court affirmed PUCO's order approving the rate increase.
Practical Implications (5)
Q: What is the practical impact of this decision for Ohio consumers?
The practical impact for Ohio consumers is that they will bear the costs associated with DP&L's clean coal project through their utility rates. While the project aimed for environmental benefits, the decision means consumers are paying for the investment, including costs incurred despite performance issues.
Q: How does this ruling affect other utility companies in Ohio regarding investments in new technology?
This ruling provides a precedent that utility companies can potentially recover costs for significant investments in new, even experimental, technologies, provided the Public Utilities Commission (PUCO) finds the investment prudent and in the public interest, even if the technology doesn't perform exactly as initially projected.
Q: What are the compliance implications for utilities following this decision?
Utilities must ensure that their applications for cost recovery, especially for novel technologies, are well-documented, demonstrating prudence and a clear benefit to the public interest. They must be prepared to justify investments even if performance metrics are not fully met, relying on PUCO's discretion.
Q: What does this case suggest about the balance between environmental goals and consumer costs for utilities?
The case suggests that Ohio's regulatory framework, as interpreted by the Supreme Court, allows for a balance where investments in potentially cleaner technologies are supported through rate recovery, even if they are costly and imperfect. The public interest in technological advancement and environmental improvement can outweigh immediate cost concerns for consumers.
Q: What is the broader business impact for energy companies in Ohio?
The decision signals that energy companies can undertake significant capital investments in new technologies, such as clean coal, with a reasonable expectation of cost recovery through regulated rates, provided they navigate the PUCO approval process effectively and demonstrate the prudence of their investments.
Historical Context (3)
Q: How does this decision fit into the historical context of utility regulation in Ohio?
This case fits into the historical context of Ohio's regulatory approach, which generally grants the Public Utilities Commission (PUCO) significant discretion to balance the interests of utilities and consumers. The court's deference to PUCO reflects a long-standing tradition of allowing the commission to adapt to evolving energy technologies and public needs.
Q: Are there previous Ohio Supreme Court cases that set a precedent for reviewing PUCO's decisions on cost recovery for innovative projects?
Yes, the Ohio Supreme Court has a history of reviewing PUCO decisions under an abuse of discretion standard. Cases involving utility rate-making and cost recovery for new infrastructure or technologies have consistently emphasized the court's limited role in second-guessing the commission's expert judgment when supported by evidence.
Q: How does this ruling compare to landmark cases on utility regulation or environmental technology investment?
While not a landmark case on the level of establishing entirely new legal doctrines, it reinforces established principles of administrative deference in utility regulation. It specifically applies these principles to the modern context of investing in advanced environmental technologies, showing how older regulatory frameworks adapt to new challenges.
Procedural Questions (5)
Q: What was the docket number in In re Application of Dayton Power & Light Co.?
The docket number for In re Application of Dayton Power & Light Co. is 2021-1473. This identifier is used to track the case through the court system.
Q: Can In re Application of Dayton Power & Light Co. be appealed?
Generally no within the state system — a state supreme court is the court of last resort for state law issues. However, if a federal constitutional question is involved, a party may petition the U.S. Supreme Court for review.
Q: How did the application by Dayton Power & Light reach the Ohio Supreme Court?
Dayton Power & Light (DP&L) initially applied to the Public Utilities Commission of Ohio (PUCO) for approval to recover costs. After PUCO issued an order approving the cost recovery, parties who disagreed with PUCO's decision appealed that order directly to the Ohio Supreme Court, as is typical for final PUCO orders.
Q: What procedural issue might have been raised by intervenors like the Office of the Ohio Consumers' Counsel?
Intervenors likely argued that PUCO's decision was not supported by sufficient evidence, that DP&L had not met its burden to prove the prudence of its investment, or that the resulting rate increase was not in the public interest. They would have challenged the factual and legal basis of PUCO's order.
Q: What was the outcome of the procedural appeal at the Ohio Supreme Court?
The Ohio Supreme Court affirmed the Public Utilities Commission of Ohio's (PUCO) order. This means the court found no procedural errors or substantive legal flaws that would warrant overturning PUCO's decision to allow DP&L to recover its clean coal project costs.
Cited Precedents
This opinion references the following precedent cases:
- Ohio Revised Code § 4909.15
- Ohio Revised Code § 4909.151
- Ohio Revised Code § 4909.153
- Ohio Revised Code § 4909.16
- Ohio Revised Code § 4928.02
- Ohio Revised Code § 4928.06
- Ohio Revised Code § 4928.143
- Ohio Revised Code § 4928.144
- Ohio Revised Code § 4928.145
- Ohio Revised Code § 4928.146
- Ohio Revised Code § 4928.147
- Ohio Revised Code § 4928.148
- Ohio Revised Code § 4928.149
- Ohio Revised Code § 4928.150
- Ohio Revised Code § 4928.151
Case Details
| Case Name | In re Application of Dayton Power & Light Co. |
| Citation | 2025 Ohio 2953 |
| Court | Ohio Supreme Court |
| Date Filed | 2025-08-22 |
| Docket Number | 2021-1473 |
| Precedential Status | Published |
| Outcome | Defendant Win |
| Disposition | affirmed |
| Impact Score | 30 / 100 |
| Complexity | moderate |
| Legal Topics | Public utility regulation, Rate recovery for utility investments, Clean coal technology cost recovery, Public Utilities Commission of Ohio (PUCO) authority, Prudence of utility investments, Public interest standard in utility regulation |
| Jurisdiction | oh |
Related Legal Resources
About This Analysis
This comprehensive multi-pass AI-generated analysis of In re Application of Dayton Power & Light Co. was produced by CaseLawBrief to help legal professionals, researchers, students, and the general public understand this court opinion in plain English. This case received our HEAVY-tier enrichment with 5 AI analysis passes covering core analysis, deep legal structure, comprehensive FAQ, multi-audience summaries, and cross-case practical intelligence.
CaseLawBrief aggregates court opinions from CourtListener, a project of the Free Law Project, and enriches them with AI-powered analysis. Our goal is to make the law more accessible and understandable to everyone, regardless of their legal background.
AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.
Related Cases
Other opinions on Public utility regulation or from the Ohio Supreme Court:
-
NC Ents., L.L.C. v. Norfolk & W. Ry. Co.
Railroad's use of spur line upheld under federal lawOhio Supreme Court · 2026-04-24
-
State ex rel. Howard v. Chief Inspector's Office
BWC accreditation rule upheld; claimant denied medical reimbursementOhio Supreme Court · 2026-04-23
-
State v. Hill
Ohio Supreme Court: Peering through fence gap is unlawful searchOhio Supreme Court · 2026-04-23
-
In re Complaint of Ohio Power Co v. Nationwide Energy Partners, L.L.C.
Court Rules Nationwide Not Obligated to Pay Ohio Power for Energy CreditsOhio Supreme Court · 2026-04-22
-
State v. J.B.
Ohio Supreme Court: Sleep deprivation alone doesn't make confession involuntaryOhio Supreme Court · 2026-04-22
-
State ex rel. Wright v. Madison Cty. Mun. Court
Acquitted defendant cannot be charged court-appointed counsel feesOhio Supreme Court · 2026-04-21
-
In re Resigantion of Greulich
Email resignation invalid if not filed with appointing authorityOhio Supreme Court · 2026-04-17
-
Disciplinary Counsel v. VanBibber
Ohio Supreme Court Disbars Attorney for Neglect and MisconductOhio Supreme Court · 2026-04-10