Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.

Headline: Contractor Not Liable for Breach; Owner Failed to Prove Damages

Citation: 2025 Ohio 5287

Court: Ohio Court of Appeals · Filed: 2025-11-24 · Docket: 2025-L-041
Published
This case reinforces the importance of proving both a material breach and specific, quantifiable damages in construction litigation. It highlights that minor defects are unlikely to support a breach of contract claim and that owners must actively mitigate their losses to recover compensation. moderate affirmed
Outcome: Defendant Win
Impact Score: 25/100 — Low-moderate impact: This case addresses specific legal issues with limited broader application.
Legal Topics: Breach of contractMaterial breachDamages mitigationConstruction defectsProof of damagesUnjust enrichment
Legal Principles: Substantial performanceDuty to mitigate damagesBurden of proof for damagesPlain error review

Brief at a Glance

A client can't claim a contractor ruined the job or seek damages without proving the problems were major and showing concrete financial losses.

  • Minor deviations in construction work are unlikely to constitute a material breach of contract.
  • The party claiming damages must provide sufficient evidence to prove the extent of their financial losses.
  • Failure to adequately mitigate damages can prevent recovery, even if a breach occurred.

Case Summary

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc., decided by Ohio Court of Appeals on November 24, 2025, resulted in a defendant win outcome. The core dispute involved a breach of contract claim where Shoregate Towers (plaintiff) alleged Ruple Builders (defendant) failed to complete construction work according to the contract. The court focused on whether Ruple Builders' actions constituted a material breach and whether Shoregate Towers adequately mitigated its damages. Ultimately, the court found that Ruple Builders did not materially breach the contract and that Shoregate Towers failed to prove its damages, leading to a judgment in favor of Ruple Builders. The court held: The court affirmed the trial court's finding that the defendant did not materially breach the contract because the alleged defects were minor and did not substantially impair the value of the work performed.. The appellate court held that the plaintiff failed to present sufficient evidence to prove its alleged damages, as the projected costs for repairs were speculative and not supported by expert testimony.. The court found that the plaintiff did not adequately mitigate its damages by failing to provide the defendant with an opportunity to cure the alleged defects before hiring another contractor.. The trial court's admission of certain evidence was reviewed and found to be within its discretion, not constituting reversible error.. The appellate court concluded that the plaintiff's claims for breach of contract and unjust enrichment were not supported by the evidence presented.. This case reinforces the importance of proving both a material breach and specific, quantifiable damages in construction litigation. It highlights that minor defects are unlikely to support a breach of contract claim and that owners must actively mitigate their losses to recover compensation.

AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.

Court Syllabus

CIVIL LAW: motion to disqualify counsel; abuse of discretion; Prof.Cond.R. 3.7(a); necessary witness; substantial hardship exception.

Case Analysis — Multiple Perspectives

Plain English (For Everyone)

Imagine you hired someone to build a deck, but they didn't finish it exactly as planned. This case says that if the mistakes weren't a big deal and didn't ruin the whole project, you might still have to pay them. You also can't just claim you lost a lot of money without proving it with solid evidence.

For Legal Practitioners

This decision reinforces the high bar for establishing a material breach in construction contracts, emphasizing that minor deviations or unproven damages are insufficient to excuse performance or justify substantial recovery. Practitioners should advise clients that failure to adequately mitigate damages, even when a breach is found, can significantly limit or negate recovery. The burden remains on the non-breaching party to prove both the materiality of the breach and the extent of their losses.

For Law Students

This case tests the doctrines of material breach and mitigation of damages in contract law. The court's finding that incomplete work did not constitute a material breach highlights the need for substantial deviation from contract terms. Furthermore, the plaintiff's failure to prove damages underscores the importance of demonstrating actual loss, not just the existence of a breach, for a successful claim. This is crucial for understanding remedies in contract disputes.

Newsroom Summary

A construction company won a lawsuit against a client who claimed the work was incomplete. The court ruled the client didn't prove the issues were serious enough to be a major breach and failed to show how they lost money, meaning they still owe the builder.

Key Holdings

The court established the following key holdings in this case:

  1. The court affirmed the trial court's finding that the defendant did not materially breach the contract because the alleged defects were minor and did not substantially impair the value of the work performed.
  2. The appellate court held that the plaintiff failed to present sufficient evidence to prove its alleged damages, as the projected costs for repairs were speculative and not supported by expert testimony.
  3. The court found that the plaintiff did not adequately mitigate its damages by failing to provide the defendant with an opportunity to cure the alleged defects before hiring another contractor.
  4. The trial court's admission of certain evidence was reviewed and found to be within its discretion, not constituting reversible error.
  5. The appellate court concluded that the plaintiff's claims for breach of contract and unjust enrichment were not supported by the evidence presented.

Key Takeaways

  1. Minor deviations in construction work are unlikely to constitute a material breach of contract.
  2. The party claiming damages must provide sufficient evidence to prove the extent of their financial losses.
  3. Failure to adequately mitigate damages can prevent recovery, even if a breach occurred.
  4. Substantial performance of a contract may be sufficient to avoid a finding of material breach.
  5. Courts require concrete proof of harm, not just the existence of a contractual violation.

Deep Legal Analysis

Procedural Posture

Shoregate Towers NS, L.L.C. (Shoregate) sued Ruple Builders, Inc. (Ruple) for breach of contract, alleging Ruple failed to complete construction of a condominium project according to the contract. The trial court granted summary judgment in favor of Ruple, finding that Shoregate had not presented sufficient evidence to establish a breach. Shoregate appealed this decision.

Rule Statements

"A breach of contract occurs when one party fails to perform its contractual obligations."
"To establish a breach of contract claim, the plaintiff must prove the existence of a contract, performance by the plaintiff, breach by the defendant, and resulting damages to the plaintiff."

Entities and Participants

Key Takeaways

  1. Minor deviations in construction work are unlikely to constitute a material breach of contract.
  2. The party claiming damages must provide sufficient evidence to prove the extent of their financial losses.
  3. Failure to adequately mitigate damages can prevent recovery, even if a breach occurred.
  4. Substantial performance of a contract may be sufficient to avoid a finding of material breach.
  5. Courts require concrete proof of harm, not just the existence of a contractual violation.

Know Your Rights

Real-world scenarios derived from this court's ruling:

Scenario: You hired a contractor to renovate your kitchen, and they finished the job, but a few tiles are slightly crooked and one cabinet door doesn't close perfectly. You refuse to pay the final invoice, claiming they breached the contract.

Your Rights: You have the right to a contract performed according to its terms. However, if the issues are minor and don't fundamentally prevent you from using the kitchen as intended, you may still be obligated to pay the contractor. You also have the right to seek damages, but you must be able to prove the financial harm caused by the specific defects.

What To Do: If you believe a contractor has breached a contract, gather evidence of the specific issues and their impact. Consult with an attorney to determine if the breach is material and to understand your obligation to pay. If you are seeking damages, meticulously document all costs incurred due to the defects and any lost income or opportunities.

Is It Legal?

Common legal questions answered by this ruling:

Is it legal to withhold payment from a contractor if the work isn't absolutely perfect?

It depends. If the imperfections are minor and don't significantly affect the overall use or value of the project, you likely cannot legally withhold payment entirely, as this may be considered a breach on your part. You may be entitled to a reduction in payment or to have the defects corrected, but you must typically pay for the substantial performance rendered.

This principle generally applies across jurisdictions, though specific contract terms and state laws may influence the outcome.

Practical Implications

For Homeowners and Property Developers

This ruling clarifies that minor construction defects or deviations from a contract do not automatically excuse payment or allow for significant damage claims. Clients must be prepared to prove that any breach was material and demonstrate concrete financial losses resulting from it, rather than simply pointing out imperfections.

For Contractors and Builders

This decision provides some protection by establishing that substantial performance can be sufficient to warrant payment, even if minor issues exist. It reinforces the need for clients to prove material breach and damages, making it harder for them to avoid payment based on trivial defects.

Related Legal Concepts

Material Breach
A breach of contract that is significant enough to destroy the contract's essent...
Mitigation of Damages
The legal principle requiring a party who has suffered a loss to take reasonable...
Substantial Performance
A doctrine in contract law where a party has performed enough of their contractu...
Breach of Contract
A failure, without legal excuse, to perform any promise that forms all or part o...

Frequently Asked Questions (43)

Comprehensive Q&A covering every aspect of this court opinion.

Basic Questions (10)

Q: What is Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. about?

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. is a case decided by Ohio Court of Appeals on November 24, 2025.

Q: What court decided Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. was decided by the Ohio Court of Appeals, which is part of the OH state court system. This is a state appellate court.

Q: When was Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. decided?

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. was decided on November 24, 2025.

Q: Who were the judges in Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

The judge in Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.: M. Lynch.

Q: What is the citation for Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

The citation for Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. is 2025 Ohio 5287. Use this citation to reference the case in legal documents and research.

Q: What is the case name and what was the main issue in Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

The case is Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc., and the central dispute revolved around a breach of contract claim. Shoregate Towers alleged that Ruple Builders failed to complete construction work as stipulated in their agreement, leading to a legal battle over the performance and damages.

Q: Who were the parties involved in the Shoregate Towers v. Ruple Builders case?

The parties in this case were Shoregate Towers NS, L.L.C., who was the plaintiff and alleged a breach of contract, and Ruple Builders, Inc., who was the defendant accused of failing to fulfill their contractual obligations.

Q: Which court decided the Shoregate Towers v. Ruple Builders case?

The case of Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. was decided by the Ohio Court of Appeals.

Q: What was the nature of the dispute between Shoregate Towers and Ruple Builders?

The dispute centered on a contract for construction work. Shoregate Towers claimed Ruple Builders breached the contract by not completing the work as agreed, while Ruple Builders likely argued they performed adequately or that Shoregate Towers' claims were unfounded.

Q: What was the ultimate outcome of the Shoregate Towers v. Ruple Builders case?

The Ohio Court of Appeals ultimately ruled in favor of Ruple Builders, Inc. The court found that Ruple Builders did not materially breach the contract and that Shoregate Towers failed to adequately prove its claimed damages.

Legal Analysis (18)

Q: Is Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. published?

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. is a published, precedential opinion. Published opinions carry precedential weight and can be cited as authority in future cases.

Q: What topics does Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. cover?

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. covers the following legal topics: Breach of Contract in Construction, Construction Negligence, Waterproofing Membrane Installation Standards, Causation in Construction Defect Cases, Damages for Property Damage, Admissibility of Evidence in Civil Litigation, Statute of Limitations for Construction Defects.

Q: What was the ruling in Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

The court ruled in favor of the defendant in Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.. Key holdings: The court affirmed the trial court's finding that the defendant did not materially breach the contract because the alleged defects were minor and did not substantially impair the value of the work performed.; The appellate court held that the plaintiff failed to present sufficient evidence to prove its alleged damages, as the projected costs for repairs were speculative and not supported by expert testimony.; The court found that the plaintiff did not adequately mitigate its damages by failing to provide the defendant with an opportunity to cure the alleged defects before hiring another contractor.; The trial court's admission of certain evidence was reviewed and found to be within its discretion, not constituting reversible error.; The appellate court concluded that the plaintiff's claims for breach of contract and unjust enrichment were not supported by the evidence presented..

Q: Why is Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. important?

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. has an impact score of 25/100, indicating limited broader impact. This case reinforces the importance of proving both a material breach and specific, quantifiable damages in construction litigation. It highlights that minor defects are unlikely to support a breach of contract claim and that owners must actively mitigate their losses to recover compensation.

Q: What precedent does Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. set?

Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. established the following key holdings: (1) The court affirmed the trial court's finding that the defendant did not materially breach the contract because the alleged defects were minor and did not substantially impair the value of the work performed. (2) The appellate court held that the plaintiff failed to present sufficient evidence to prove its alleged damages, as the projected costs for repairs were speculative and not supported by expert testimony. (3) The court found that the plaintiff did not adequately mitigate its damages by failing to provide the defendant with an opportunity to cure the alleged defects before hiring another contractor. (4) The trial court's admission of certain evidence was reviewed and found to be within its discretion, not constituting reversible error. (5) The appellate court concluded that the plaintiff's claims for breach of contract and unjust enrichment were not supported by the evidence presented.

Q: What are the key holdings in Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

1. The court affirmed the trial court's finding that the defendant did not materially breach the contract because the alleged defects were minor and did not substantially impair the value of the work performed. 2. The appellate court held that the plaintiff failed to present sufficient evidence to prove its alleged damages, as the projected costs for repairs were speculative and not supported by expert testimony. 3. The court found that the plaintiff did not adequately mitigate its damages by failing to provide the defendant with an opportunity to cure the alleged defects before hiring another contractor. 4. The trial court's admission of certain evidence was reviewed and found to be within its discretion, not constituting reversible error. 5. The appellate court concluded that the plaintiff's claims for breach of contract and unjust enrichment were not supported by the evidence presented.

Q: What cases are related to Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

Precedent cases cited or related to Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.: Galmish v. Cicchini, 917 N.E.2d 334 (Ohio 2009); Lake Ridge Academy v. Carney, 664 N.E.2d 1358 (Ohio 1996); F.T.D. Corp. v. Am. Express Travel Related Servs. Co., 870 N.E.2d 1211 (Ohio 2007).

Q: Did the court find that Ruple Builders materially breached the construction contract?

No, the court found that Ruple Builders did not materially breach the contract. This means that any alleged failures by Ruple Builders were not significant enough to excuse Shoregate Towers from its own contractual obligations or to justify the damages sought.

Q: What legal standard did the court apply to determine if the contract was breached?

The court applied the standard for material breach of contract. A material breach is a significant failure to perform that goes to the heart of the contract, substantially depriving the injured party of the benefit they expected.

Q: What did Shoregate Towers need to prove regarding its damages?

Shoregate Towers needed to prove its damages with sufficient evidence to establish the extent of their losses resulting from Ruple Builders' alleged breach. The court found that Shoregate Towers failed to meet this burden of proof.

Q: What is the significance of a 'material breach' in contract law, as discussed in this case?

A material breach is a serious violation of a contract's terms that allows the non-breaching party to terminate the contract and sue for damages. The court's finding that Ruple Builders' actions did not constitute a material breach was crucial to the final judgment.

Q: Did the court consider whether Shoregate Towers took steps to mitigate its damages?

Yes, the court considered whether Shoregate Towers adequately mitigated its damages. Mitigation requires the non-breaching party to take reasonable steps to minimize their losses after a breach occurs, and the court found Shoregate Towers failed in this regard.

Q: What does it mean for a party to 'mitigate damages' in a contract dispute?

Mitigating damages means that the party claiming harm must take reasonable actions to reduce the amount of loss they suffer. For example, if a contractor fails to complete work, the owner should seek other reasonable options to finish the project rather than letting costs escalate unnecessarily.

Q: How does the concept of 'failure to prove damages' affect a breach of contract claim?

Even if a breach of contract is proven, the plaintiff must still demonstrate the specific amount of financial loss they incurred as a direct result of that breach. If damages cannot be proven with reasonable certainty, the plaintiff may not recover compensation.

Q: What is the burden of proof in a breach of contract case like Shoregate Towers v. Ruple Builders?

In a breach of contract case, the plaintiff (Shoregate Towers) bears the burden of proving that a contract existed, that the defendant (Ruple Builders) breached it, and that the plaintiff suffered damages as a result of that breach.

Q: What legal doctrines were central to the court's analysis in Shoregate Towers v. Ruple Builders?

The central legal doctrines were material breach of contract and the duty to mitigate damages. The court's analysis hinged on whether Ruple Builders' actions met the threshold for a material breach and whether Shoregate Towers fulfilled its obligation to minimize its losses.

Q: How did the court's finding on 'material breach' impact the final judgment?

The court's finding that Ruple Builders did not materially breach the contract was dispositive. It meant that Shoregate Towers could not claim the contract was fundamentally broken by Ruple Builders, thus limiting Shoregate's ability to recover damages for the entire project's cost or completion.

Q: What specific evidence might Shoregate Towers have presented to prove damages?

Shoregate Towers could have presented evidence such as invoices for work done by replacement contractors, expert testimony on the cost of completing the project, documentation of delays and their financial impact, and evidence of any lost profits directly attributable to the breach.

Practical Implications (5)

Q: How does Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. affect me?

This case reinforces the importance of proving both a material breach and specific, quantifiable damages in construction litigation. It highlights that minor defects are unlikely to support a breach of contract claim and that owners must actively mitigate their losses to recover compensation. As a decision from a state appellate court, its reach is limited to the state jurisdiction. This case is moderate in legal complexity to understand.

Q: What are the practical implications of the Shoregate Towers v. Ruple Builders decision for construction companies?

For construction companies like Ruple Builders, this decision reinforces the importance of clear contracts and diligent performance. It suggests that courts may scrutinize claims of material breach and require solid proof of damages from the party alleging the breach.

Q: How does this ruling affect property owners who hire contractors?

Property owners like Shoregate Towers must be prepared to demonstrate not only a breach but also the specific financial losses incurred. They also have a duty to take reasonable steps to minimize their damages, otherwise, their claims may be reduced or denied.

Q: What advice would this case offer to businesses entering into construction contracts?

Businesses should ensure contracts clearly define scope, timelines, and quality standards. They should also maintain detailed records of performance and any issues that arise, and be prepared to act reasonably to mitigate potential losses if a dispute occurs.

Q: What are the potential consequences for a party that fails to mitigate damages?

Failing to mitigate damages can lead to a reduction or complete denial of any awarded compensation. The court will not allow a party to recover losses that could have been reasonably avoided through their own actions.

Historical Context (2)

Q: Does this case set a new precedent in Ohio contract law?

While this case applies existing principles of contract law regarding material breach and mitigation of damages, its specific application and reasoning contribute to the body of case law in Ohio. It reinforces how these doctrines are evaluated in the context of construction disputes.

Q: How does this ruling compare to other landmark Ohio breach of contract cases?

This case aligns with the general principle in Ohio contract law that a party must prove both a breach and resulting damages. It emphasizes the distinction between minor defects and a material breach that fundamentally undermines the contract's purpose.

Procedural Questions (5)

Q: What was the docket number in Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc.?

The docket number for Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. is 2025-L-041. This identifier is used to track the case through the court system.

Q: Can Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. be appealed?

Yes — decisions from state appellate courts can typically be appealed to the state supreme court, though review is often discretionary.

Q: What procedural steps might have led this case to the Ohio Court of Appeals?

Typically, a case like this would proceed from a trial court (e.g., a county court of common pleas) where a judgment was initially rendered. One of the parties, likely Shoregate Towers if they lost at trial, would then appeal to the Ohio Court of Appeals, arguing that the trial court made legal errors.

Q: What is the role of the Ohio Court of Appeals in reviewing trial court decisions?

The Ohio Court of Appeals reviews decisions from trial courts for errors of law. They do not typically re-hear evidence or retry the case but examine the trial record and legal arguments to determine if the lower court applied the law correctly.

Q: Could this decision be appealed further, and to which court?

Potentially, yes. The losing party could seek to appeal this decision to the Supreme Court of Ohio. However, the Supreme Court of Ohio has discretion over which cases it chooses to hear, typically selecting those involving significant legal questions or conflicts among lower courts.

Cited Precedents

This opinion references the following precedent cases:

  • Galmish v. Cicchini, 917 N.E.2d 334 (Ohio 2009)
  • Lake Ridge Academy v. Carney, 664 N.E.2d 1358 (Ohio 1996)
  • F.T.D. Corp. v. Am. Express Travel Related Servs. Co., 870 N.E.2d 1211 (Ohio 2007)

Case Details

Case NameShoregate Towers NS, L.L.C. v. Ruple Builders, Inc.
Citation2025 Ohio 5287
CourtOhio Court of Appeals
Date Filed2025-11-24
Docket Number2025-L-041
Precedential StatusPublished
OutcomeDefendant Win
Dispositionaffirmed
Impact Score25 / 100
SignificanceThis case reinforces the importance of proving both a material breach and specific, quantifiable damages in construction litigation. It highlights that minor defects are unlikely to support a breach of contract claim and that owners must actively mitigate their losses to recover compensation.
Complexitymoderate
Legal TopicsBreach of contract, Material breach, Damages mitigation, Construction defects, Proof of damages, Unjust enrichment
Jurisdictionoh

Related Legal Resources

Ohio Court of Appeals Opinions Breach of contractMaterial breachDamages mitigationConstruction defectsProof of damagesUnjust enrichment oh Jurisdiction Know Your Rights: Breach of contractKnow Your Rights: Material breachKnow Your Rights: Damages mitigation Home Search Cases Is It Legal? 2025 Cases All Courts All Topics States Rankings Breach of contract GuideMaterial breach Guide Substantial performance (Legal Term)Duty to mitigate damages (Legal Term)Burden of proof for damages (Legal Term)Plain error review (Legal Term) Breach of contract Topic HubMaterial breach Topic HubDamages mitigation Topic Hub

About This Analysis

This comprehensive multi-pass AI-generated analysis of Shoregate Towers NS, L.L.C. v. Ruple Builders, Inc. was produced by CaseLawBrief to help legal professionals, researchers, students, and the general public understand this court opinion in plain English. This case received our HEAVY-tier enrichment with 5 AI analysis passes covering core analysis, deep legal structure, comprehensive FAQ, multi-audience summaries, and cross-case practical intelligence.

CaseLawBrief aggregates court opinions from CourtListener, a project of the Free Law Project, and enriches them with AI-powered analysis. Our goal is to make the law more accessible and understandable to everyone, regardless of their legal background.

AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.

Related Cases

Other opinions on Breach of contract or from the Ohio Court of Appeals:

  • State v. Goodson
    Probable Cause Justifies Warrantless Vehicle Search for Drugs
    Ohio Court of Appeals · 2026-04-24
  • State v. Sanchez
    Statements to Police Deemed Voluntary, Conviction Affirmed
    Ohio Court of Appeals · 2026-04-24
  • State v. Castaneda
    Ohio Court Affirms Suppression of Evidence from Warrantless Vehicle Search
    Ohio Court of Appeals · 2026-04-24
  • State v. Mitchell
    Court suppresses evidence from warrantless vehicle search due to lack of probable cause
    Ohio Court of Appeals · 2026-04-24
  • State v. Thompson
    Ohio Court Affirms Warrantless Vehicle Search Based on Probable Cause
    Ohio Court of Appeals · 2026-04-24
  • State v. Gore
    Warrantless vehicle search after traffic stop deemed unlawful
    Ohio Court of Appeals · 2026-04-24
  • Helton v. Kettering Medical Ctr.
    Medical Malpractice Claim Fails Due to Insufficient Evidence of Negligence
    Ohio Court of Appeals · 2026-04-24
  • In re C.P.
    Ohio Court Allows Reconsideration of No-Contact Order for Child Visitation
    Ohio Court of Appeals · 2026-04-24