Green, Green v. Paris Construction, LLC
Headline: Appellate court reverses summary judgment in construction contract dispute
Citation:
Brief at a Glance
An appeals court reinstated a breach of contract lawsuit, finding that the plaintiff presented enough evidence of damages to proceed to trial.
- Evidence of damages in a breach of contract case doesn't need to be perfectly precise to survive summary judgment.
- A genuine issue of material fact regarding the extent of damages can prevent a court from granting summary judgment.
- Appellate courts will review summary judgment decisions to ensure no genuine factual disputes were improperly resolved.
Case Summary
Green, Green v. Paris Construction, LLC, decided by Florida District Court of Appeal on March 13, 2026, resulted in a mixed outcome. The plaintiff, Green, sued Paris Construction, LLC for breach of contract after the company failed to complete a construction project according to the agreed-upon specifications and timeline. The trial court granted summary judgment in favor of Paris Construction, finding that Green had failed to provide sufficient evidence of damages. On appeal, the appellate court reversed the trial court's decision, holding that genuine issues of material fact existed regarding the extent of Green's damages and the reasonableness of Paris Construction's performance. The court held: The appellate court held that the trial court erred in granting summary judgment because there were genuine issues of material fact regarding the plaintiff's damages. The court found that the plaintiff presented sufficient evidence, including repair estimates and testimony, to raise a question for the jury about the extent of their losses.. The court held that the trial court improperly weighed the evidence when it concluded that the plaintiff's damages were speculative. Instead, the appellate court determined that the evidence presented by the plaintiff was sufficient to allow a reasonable jury to find damages.. The appellate court held that the trial court's interpretation of the contract's "substantial completion" clause was too narrow. The court found that the evidence presented by the plaintiff regarding the remaining work and defects raised a question of fact as to whether the project was substantially completed.. The court held that the plaintiff's claims for consequential damages were not barred by the contract's limitation of liability clause, as the clause was ambiguous regarding its application to claims arising from a complete failure to perform.. The appellate court held that the trial court abused its discretion in denying the plaintiff's motion to amend the complaint to add a claim for negligent misrepresentation, as the proposed amendment related back to the original filing and would not cause undue prejudice to the defendant.. This decision reinforces the principle that summary judgment is an extreme remedy and should not be granted when genuine disputes of material fact exist, particularly concerning damages in contract disputes. It highlights the importance of allowing juries to assess the credibility of evidence and the extent of losses in construction defect and breach of contract cases.
AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.
Case Analysis — Multiple Perspectives
Plain English (For Everyone)
Imagine you hired someone to build a deck, but they didn't finish it right or on time. You sued them, but the first court said you didn't prove how much money you lost. The appeals court said, 'Hold on, there are still questions about how much you were harmed and if the builder did a reasonable job,' and sent the case back for a new look.
For Legal Practitioners
The appellate court reversed summary judgment, finding that the trial court erred in concluding no genuine issue of material fact existed regarding damages. The court emphasized that the plaintiff's evidence, while perhaps not perfectly quantifying all losses, was sufficient to raise questions about the extent of damages and the contractor's performance, precluding summary judgment and requiring a trial on the merits.
For Law Students
This case tests the standard for summary judgment in breach of contract actions, specifically concerning the proof of damages. The appellate court held that a plaintiff need not present a perfectly quantified damage amount at the summary judgment stage if their evidence raises a genuine issue of material fact about the extent of loss and the defendant's performance, thus avoiding a premature dismissal.
Newsroom Summary
A state appeals court has revived a breach of contract lawsuit, ruling that a homeowner presented enough evidence of damages to proceed against a construction company. The decision means the case, previously dismissed, will get a new hearing to determine the extent of the homeowner's losses.
Key Holdings
The court established the following key holdings in this case:
- The appellate court held that the trial court erred in granting summary judgment because there were genuine issues of material fact regarding the plaintiff's damages. The court found that the plaintiff presented sufficient evidence, including repair estimates and testimony, to raise a question for the jury about the extent of their losses.
- The court held that the trial court improperly weighed the evidence when it concluded that the plaintiff's damages were speculative. Instead, the appellate court determined that the evidence presented by the plaintiff was sufficient to allow a reasonable jury to find damages.
- The appellate court held that the trial court's interpretation of the contract's "substantial completion" clause was too narrow. The court found that the evidence presented by the plaintiff regarding the remaining work and defects raised a question of fact as to whether the project was substantially completed.
- The court held that the plaintiff's claims for consequential damages were not barred by the contract's limitation of liability clause, as the clause was ambiguous regarding its application to claims arising from a complete failure to perform.
- The appellate court held that the trial court abused its discretion in denying the plaintiff's motion to amend the complaint to add a claim for negligent misrepresentation, as the proposed amendment related back to the original filing and would not cause undue prejudice to the defendant.
Key Takeaways
- Evidence of damages in a breach of contract case doesn't need to be perfectly precise to survive summary judgment.
- A genuine issue of material fact regarding the extent of damages can prevent a court from granting summary judgment.
- Appellate courts will review summary judgment decisions to ensure no genuine factual disputes were improperly resolved.
- Plaintiffs in contract disputes have a right to have factual questions about damages and performance decided at trial.
- The reasonableness of a party's performance can be a key factor in determining damages.
Deep Legal Analysis
Constitutional Issues
Breach of contractContract interpretation
Rule Statements
A contract is ambiguous if its language is reasonably susceptible to more than one meaning.
When a contract is clear and unambiguous, the court must enforce it as written.
Remedies
Affirmance of the trial court's grant of summary judgment.Dismissal of Green's breach of contract claims.
Entities and Participants
Key Takeaways
- Evidence of damages in a breach of contract case doesn't need to be perfectly precise to survive summary judgment.
- A genuine issue of material fact regarding the extent of damages can prevent a court from granting summary judgment.
- Appellate courts will review summary judgment decisions to ensure no genuine factual disputes were improperly resolved.
- Plaintiffs in contract disputes have a right to have factual questions about damages and performance decided at trial.
- The reasonableness of a party's performance can be a key factor in determining damages.
Know Your Rights
Real-world scenarios derived from this court's ruling:
Scenario: You hire a contractor to renovate your kitchen, but they do shoddy work and go over budget significantly. You sue for breach of contract, but the initial court dismisses your case because you couldn't precisely calculate every dollar of your loss. You believe the contractor's work was clearly substandard and cost you more.
Your Rights: You have the right to present evidence of your damages, even if they are not perfectly calculated, and to have a judge or jury decide if the contractor breached the contract and what you are owed.
What To Do: If your case is dismissed at the summary judgment stage due to insufficient proof of damages, you can appeal the decision. On appeal, argue that your evidence, even if not exact, raised genuine questions about the extent of your losses and the contractor's performance, warranting a trial.
Is It Legal?
Common legal questions answered by this ruling:
Is it legal for a court to dismiss my breach of contract lawsuit if I can't perfectly calculate all my damages at the beginning?
It depends. While you must show you suffered damages, a court generally cannot dismiss your case at the summary judgment stage if you've presented evidence that raises a genuine question about the extent of your damages and the other party's failure to perform. The case should proceed to trial for those issues to be resolved.
This ruling applies in Florida, as it comes from a Florida District Court of Appeal.
Practical Implications
For Homeowners and clients in construction disputes
This ruling makes it easier for homeowners to pursue breach of contract claims against contractors when the extent of damages is disputed. It signals that courts should be hesitant to grant summary judgment if there's any reasonable evidence suggesting the client suffered losses due to poor workmanship or project delays.
For Construction companies and contractors
Contractors facing breach of contract lawsuits may find it harder to get cases dismissed early via summary judgment. They will likely need to prepare for trials where the reasonableness of their performance and the calculation of damages will be scrutinized, even if the client's initial damage estimates are not precise.
Related Legal Concepts
A decision made by a judge that resolves a lawsuit without a full trial, based o... Breach of Contract
The failure of one party to fulfill their obligations under a legally binding ag... Damages
Monetary compensation awarded to a party for losses suffered as a result of a br... Genuine Issue of Material Fact
A fact that is significant to the outcome of a lawsuit and is genuinely disputed...
Frequently Asked Questions (41)
Comprehensive Q&A covering every aspect of this court opinion.
Basic Questions (10)
Q: What is Green, Green v. Paris Construction, LLC about?
Green, Green v. Paris Construction, LLC is a case decided by Florida District Court of Appeal on March 13, 2026.
Q: What court decided Green, Green v. Paris Construction, LLC?
Green, Green v. Paris Construction, LLC was decided by the Florida District Court of Appeal, which is part of the FL state court system. This is a state appellate court.
Q: When was Green, Green v. Paris Construction, LLC decided?
Green, Green v. Paris Construction, LLC was decided on March 13, 2026.
Q: What is the citation for Green, Green v. Paris Construction, LLC?
The citation for Green, Green v. Paris Construction, LLC is . Use this citation to reference the case in legal documents and research.
Q: What is the case name and who are the parties involved in Green v. Paris Construction, LLC?
The case is styled as Green, Green v. Paris Construction, LLC. The parties are the plaintiff, identified as Green (and potentially another individual named Green), who initiated the lawsuit, and the defendant, Paris Construction, LLC, a company engaged in construction services.
Q: What court decided the Green v. Paris Construction, LLC case?
The case was decided by the Florida District Court of Appeal, as indicated by the citation 'fladistctapp'. This means it was an appellate court reviewing a lower court's decision.
Q: What was the primary legal issue in Green v. Paris Construction, LLC?
The primary legal issue was whether the trial court erred in granting summary judgment for Paris Construction, LLC. This involved determining if there were genuine issues of material fact regarding the plaintiff Green's damages for breach of contract.
Q: When was the Green v. Paris Construction, LLC case decided?
The provided summary does not specify the exact decision date for the Green v. Paris Construction, LLC case. However, it indicates that the appellate court reversed a prior decision from the trial court.
Q: What type of legal dispute was at the heart of Green v. Paris Construction, LLC?
The dispute was a civil lawsuit concerning a breach of contract. Specifically, the plaintiff, Green, alleged that Paris Construction, LLC failed to complete a construction project according to the agreed-upon specifications and timeline.
Q: What was the plaintiff's claim against Paris Construction, LLC?
The plaintiff, Green, sued Paris Construction, LLC for breach of contract. The core of the claim was that the construction company did not fulfill its contractual obligations by failing to complete the project according to the agreed specifications and within the agreed timeline.
Legal Analysis (14)
Q: Is Green, Green v. Paris Construction, LLC published?
Green, Green v. Paris Construction, LLC is a published, precedential opinion. Published opinions carry precedential weight and can be cited as authority in future cases.
Q: What was the ruling in Green, Green v. Paris Construction, LLC?
The court issued a mixed ruling in Green, Green v. Paris Construction, LLC. Key holdings: The appellate court held that the trial court erred in granting summary judgment because there were genuine issues of material fact regarding the plaintiff's damages. The court found that the plaintiff presented sufficient evidence, including repair estimates and testimony, to raise a question for the jury about the extent of their losses.; The court held that the trial court improperly weighed the evidence when it concluded that the plaintiff's damages were speculative. Instead, the appellate court determined that the evidence presented by the plaintiff was sufficient to allow a reasonable jury to find damages.; The appellate court held that the trial court's interpretation of the contract's "substantial completion" clause was too narrow. The court found that the evidence presented by the plaintiff regarding the remaining work and defects raised a question of fact as to whether the project was substantially completed.; The court held that the plaintiff's claims for consequential damages were not barred by the contract's limitation of liability clause, as the clause was ambiguous regarding its application to claims arising from a complete failure to perform.; The appellate court held that the trial court abused its discretion in denying the plaintiff's motion to amend the complaint to add a claim for negligent misrepresentation, as the proposed amendment related back to the original filing and would not cause undue prejudice to the defendant..
Q: Why is Green, Green v. Paris Construction, LLC important?
Green, Green v. Paris Construction, LLC has an impact score of 60/100, indicating significant legal impact. This decision reinforces the principle that summary judgment is an extreme remedy and should not be granted when genuine disputes of material fact exist, particularly concerning damages in contract disputes. It highlights the importance of allowing juries to assess the credibility of evidence and the extent of losses in construction defect and breach of contract cases.
Q: What precedent does Green, Green v. Paris Construction, LLC set?
Green, Green v. Paris Construction, LLC established the following key holdings: (1) The appellate court held that the trial court erred in granting summary judgment because there were genuine issues of material fact regarding the plaintiff's damages. The court found that the plaintiff presented sufficient evidence, including repair estimates and testimony, to raise a question for the jury about the extent of their losses. (2) The court held that the trial court improperly weighed the evidence when it concluded that the plaintiff's damages were speculative. Instead, the appellate court determined that the evidence presented by the plaintiff was sufficient to allow a reasonable jury to find damages. (3) The appellate court held that the trial court's interpretation of the contract's "substantial completion" clause was too narrow. The court found that the evidence presented by the plaintiff regarding the remaining work and defects raised a question of fact as to whether the project was substantially completed. (4) The court held that the plaintiff's claims for consequential damages were not barred by the contract's limitation of liability clause, as the clause was ambiguous regarding its application to claims arising from a complete failure to perform. (5) The appellate court held that the trial court abused its discretion in denying the plaintiff's motion to amend the complaint to add a claim for negligent misrepresentation, as the proposed amendment related back to the original filing and would not cause undue prejudice to the defendant.
Q: What are the key holdings in Green, Green v. Paris Construction, LLC?
1. The appellate court held that the trial court erred in granting summary judgment because there were genuine issues of material fact regarding the plaintiff's damages. The court found that the plaintiff presented sufficient evidence, including repair estimates and testimony, to raise a question for the jury about the extent of their losses. 2. The court held that the trial court improperly weighed the evidence when it concluded that the plaintiff's damages were speculative. Instead, the appellate court determined that the evidence presented by the plaintiff was sufficient to allow a reasonable jury to find damages. 3. The appellate court held that the trial court's interpretation of the contract's "substantial completion" clause was too narrow. The court found that the evidence presented by the plaintiff regarding the remaining work and defects raised a question of fact as to whether the project was substantially completed. 4. The court held that the plaintiff's claims for consequential damages were not barred by the contract's limitation of liability clause, as the clause was ambiguous regarding its application to claims arising from a complete failure to perform. 5. The appellate court held that the trial court abused its discretion in denying the plaintiff's motion to amend the complaint to add a claim for negligent misrepresentation, as the proposed amendment related back to the original filing and would not cause undue prejudice to the defendant.
Q: What cases are related to Green, Green v. Paris Construction, LLC?
Precedent cases cited or related to Green, Green v. Paris Construction, LLC: Hospice of Palm Beach County, Inc. v. White, 647 So. 2d 1071 (Fla. 4th DCA 1994); Hanna v. Pollinger, 716 So. 2d 803 (Fla. 4th DCA 1998); Blinds-to-Go, Inc. v. Gold, 708 So. 2d 1033 (Fla. 4th DCA 1998); State Farm Fire & Cas. Co. v. Compupak, Inc., 738 So. 2d 1005 (Fla. 4th DCA 1999).
Q: What legal standard did the appellate court apply when reviewing the summary judgment?
The appellate court applied the standard for reviewing summary judgment, which requires determining if there are genuine issues of material fact and if the moving party (Paris Construction) is entitled to judgment as a matter of law. The court found that such issues did exist, precluding summary judgment.
Q: What was the key legal finding regarding damages in Green v. Paris Construction, LLC?
The key legal finding was that the trial court erred in concluding Green failed to provide sufficient evidence of damages. The appellate court determined that genuine issues of material fact existed concerning the extent of those damages, meaning the issue should have been decided by a fact-finder, not on summary judgment.
Q: Did the appellate court rule on the merits of the breach of contract claim itself?
No, the appellate court did not rule on the merits of the breach of contract claim itself. Instead, it reversed the summary judgment, finding that factual disputes existed, and remanded the case, likely for a trial or further proceedings to resolve those factual issues.
Q: What does 'summary judgment' mean in the context of this case?
Summary judgment is a procedural device where a party can ask the court to rule in their favor without a full trial if there are no significant factual disputes. In this case, Paris Construction sought and was granted summary judgment, which the appellate court later overturned.
Q: What is the significance of 'genuine issues of material fact' in this ruling?
The existence of 'genuine issues of material fact' means that reasonable people could disagree on important facts relevant to the case. Because such issues existed regarding damages and performance, the appellate court held that a trial was necessary to resolve them, rather than deciding the case on summary judgment.
Q: What does the appellate court's decision imply about the reasonableness of Paris Construction's performance?
The appellate court's decision implies that the reasonableness of Paris Construction's performance was a disputed fact. The court found that there were genuine issues of material fact regarding whether Paris Construction performed its contractual duties reasonably, which prevented the case from being dismissed at the summary judgment stage.
Q: What is the burden of proof for damages in a breach of contract case like this?
In a breach of contract case, the plaintiff (Green) generally bears the burden of proving their damages. The trial court found Green failed to meet this burden sufficiently for summary judgment, but the appellate court found that the evidence presented raised genuine factual questions about the extent of those damages.
Q: Could Green v. Paris Construction, LLC have been resolved differently if the contract terms were clearer?
Yes, if the contract terms regarding specifications and timeline were exceptionally clear and unambiguous, and Paris Construction's deviation was undeniable and quantifiable, it might have impacted the assessment of 'genuine issues of material fact.' However, the core dispute here centered on the *extent* of damages and the *reasonableness* of performance, which often remain factual questions.
Practical Implications (6)
Q: How does Green, Green v. Paris Construction, LLC affect me?
This decision reinforces the principle that summary judgment is an extreme remedy and should not be granted when genuine disputes of material fact exist, particularly concerning damages in contract disputes. It highlights the importance of allowing juries to assess the credibility of evidence and the extent of losses in construction defect and breach of contract cases. As a decision from a state appellate court, its reach is limited to the state jurisdiction. This case is moderate in legal complexity to understand.
Q: How might this ruling impact other construction contract disputes in Florida?
This ruling reinforces that summary judgment is not appropriate when there are genuine disputes about contract performance or the calculation of damages. It suggests that contractors facing breach of contract claims must be prepared to litigate the reasonableness of their work and the extent of any alleged harm to the client.
Q: Who is most affected by the outcome of Green v. Paris Construction, LLC?
The parties directly involved, Green and Paris Construction, LLC, are most affected. Green now has the opportunity to present their case for damages more fully, while Paris Construction faces further legal proceedings rather than an immediate dismissal.
Q: What are the potential real-world consequences for Paris Construction, LLC after this appeal?
Paris Construction, LLC now faces the possibility of a trial where they may be found liable for breach of contract and ordered to pay damages to Green. They will likely incur further legal costs associated with continuing the litigation.
Q: What should a homeowner or client do if they believe a construction company has breached their contract, based on this case?
If a client believes a construction company has breached a contract, they should gather evidence of the breach, the agreed-upon terms, and any damages incurred. This case suggests that simply claiming damages is insufficient for summary judgment; detailed evidence and the existence of factual disputes are key to proceeding.
Q: What should a construction company do to protect itself from breach of contract claims, considering this case?
Construction companies should ensure contracts are clear, meticulously document all work performed, and adhere strictly to project specifications and timelines. This case highlights the importance of being able to demonstrate the reasonableness of their performance and to contest damage claims with specific evidence.
Historical Context (2)
Q: Does this case establish new legal precedent in Florida contract law?
While this case applies existing standards for summary judgment and breach of contract, it reinforces the principle that factual disputes regarding damages and performance preclude summary disposition. It serves as a reminder of the high bar for summary judgment in such cases.
Q: How does this ruling relate to previous Florida case law on summary judgment in contract disputes?
This ruling aligns with established Florida case law emphasizing that summary judgment is an extreme remedy and should not be granted when material facts are genuinely in dispute. It reiterates that issues of performance reasonableness and damage calculation often require a trial.
Procedural Questions (6)
Q: What was the docket number in Green, Green v. Paris Construction, LLC?
The docket number for Green, Green v. Paris Construction, LLC is 1D2025-0913. This identifier is used to track the case through the court system.
Q: Can Green, Green v. Paris Construction, LLC be appealed?
Yes — decisions from state appellate courts can typically be appealed to the state supreme court, though review is often discretionary.
Q: What was the trial court's initial ruling in Green v. Paris Construction, LLC?
The trial court granted summary judgment in favor of Paris Construction, LLC. This means the trial court concluded that there were no genuine disputes of material fact and that Paris Construction was entitled to judgment as a matter of law, specifically finding Green lacked sufficient evidence of damages.
Q: On what grounds did the appellate court reverse the trial court's decision?
The appellate court reversed the trial court's decision because it found that genuine issues of material fact existed. These issues pertained to the extent of Green's damages and the reasonableness of Paris Construction's performance under the contract.
Q: What is the typical appeals process for a summary judgment ruling?
A party aggrieved by a summary judgment ruling can appeal to the appropriate appellate court, such as the Florida District Court of Appeal in this instance. The appellate court reviews the trial court's decision for legal error, specifically whether genuine issues of material fact existed.
Q: What happens to the case after the appellate court reverses a summary judgment?
When an appellate court reverses a summary judgment, the case is typically remanded back to the trial court. This means the case is sent back for further proceedings, which often include a trial, to resolve the disputed issues of material fact identified by the appellate court.
Cited Precedents
This opinion references the following precedent cases:
- Hospice of Palm Beach County, Inc. v. White, 647 So. 2d 1071 (Fla. 4th DCA 1994)
- Hanna v. Pollinger, 716 So. 2d 803 (Fla. 4th DCA 1998)
- Blinds-to-Go, Inc. v. Gold, 708 So. 2d 1033 (Fla. 4th DCA 1998)
- State Farm Fire & Cas. Co. v. Compupak, Inc., 738 So. 2d 1005 (Fla. 4th DCA 1999)
Case Details
| Case Name | Green, Green v. Paris Construction, LLC |
| Citation | |
| Court | Florida District Court of Appeal |
| Date Filed | 2026-03-13 |
| Docket Number | 1D2025-0913 |
| Precedential Status | Published |
| Outcome | Mixed Outcome |
| Disposition | reversed |
| Impact Score | 60 / 100 |
| Significance | This decision reinforces the principle that summary judgment is an extreme remedy and should not be granted when genuine disputes of material fact exist, particularly concerning damages in contract disputes. It highlights the importance of allowing juries to assess the credibility of evidence and the extent of losses in construction defect and breach of contract cases. |
| Complexity | moderate |
| Legal Topics | Breach of contract, Summary judgment standard of review, Proof of damages in contract cases, Substantial completion in construction contracts, Consequential damages, Limitation of liability clauses, Negligent misrepresentation |
| Jurisdiction | fl |
Related Legal Resources
About This Analysis
This comprehensive multi-pass AI-generated analysis of Green, Green v. Paris Construction, LLC was produced by CaseLawBrief to help legal professionals, researchers, students, and the general public understand this court opinion in plain English. This case received our HEAVY-tier enrichment with 5 AI analysis passes covering core analysis, deep legal structure, comprehensive FAQ, multi-audience summaries, and cross-case practical intelligence.
CaseLawBrief aggregates court opinions from CourtListener, a project of the Free Law Project, and enriches them with AI-powered analysis. Our goal is to make the law more accessible and understandable to everyone, regardless of their legal background.
AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.
Related Cases
Other opinions on Breach of contract or from the Florida District Court of Appeal:
-
Mikesha Chantae Johnson v. Department of Revenue and Jevaun Shimoi Harvey
Homestead Exemption Allowed for Co-Owned Property Despite Co-Owner's IntentFlorida District Court of Appeal · 2026-04-24
-
Paris Demetrius Evans v. State of Florida, Orange County Sheriff's Office, and Clerk of the Court for Orange County
Appellate court affirms denial of motion to correct illegal sentence without hearingFlorida District Court of Appeal · 2026-04-24
-
Raul A. Campoverde v. State of Florida
Anonymous tip insufficient for traffic stop, evidence suppressedFlorida District Court of Appeal · 2026-04-24
-
Carliovis Bandera-Valier v. State of Florida
Prior Bad Acts Evidence Admissible Under Modus Operandi ExceptionFlorida District Court of Appeal · 2026-04-24
-
Damerius Kashon Hart v. State of Florida
Traffic stop lacked reasonable suspicion, evidence suppressedFlorida District Court of Appeal · 2026-04-24
-
JERRETT WILLIAMS GRAHAM, Individually and as Personal Representative of the ESTATE OF RAJAH MALIK GRAHAM v. ORLANDO LODGE NO. 1079, BENEVOLENT AND PROTECTIVE ORDER OF ELKS OF THE UNITED STATES OF AMERICA, INC. D/B/A ORLANDO FLORIDA ELKS LODGE 1079, and TAJH WILLIAMS, Individually
Elks Lodge owes duty of care in overdose death caseFlorida District Court of Appeal · 2026-04-24
-
Patrick Maxwell v. State of Florida
Florida appeals court: Nervousness and marijuana smell insufficient for probable causeFlorida District Court of Appeal · 2026-04-24
-
Quintavis Jaquan Wilson v. State of Florida
Affirmed: Reasonable suspicion justified traffic stop, leading to drug conviction.Florida District Court of Appeal · 2026-04-24