Nahas Constr. Corp. v. Brustoski

Headline: Contractor awarded full payment despite homeowner's defect claims

Citation: 2026 Ohio 1362

Court: Ohio Court of Appeals · Filed: 2026-04-15 · Docket: 31600
Published
This case reinforces the principle of substantial performance in construction law, providing clarity for contractors and homeowners. It emphasizes that minor defects will not necessarily prevent a contractor from recovering the full contract price, provided the core purpose of the agreement has been fulfilled, and highlights the homeowner's burden to prove the materiality of alleged defects. moderate affirmed
Outcome: Plaintiff Win
Impact Score: 25/100 — Low-moderate impact: This case addresses specific legal issues with limited broader application.
Legal Topics: Breach of contractSubstantial performance doctrineMateriality of defects in construction contractsBurden of proof in contract disputesDamages for construction defects
Legal Principles: Substantial performanceBurden of proofContract interpretation

Brief at a Glance

Contractors get paid the full price for home renovations, minus the cost of fixing proven defects, as long as the main job is substantially completed.

  • Contractors are entitled to the contract price if they have substantially performed their obligations.
  • The burden is on the homeowner to prove that alleged defects are material and prevented substantial performance.
  • Minor deviations or cosmetic flaws do not typically constitute a material breach of contract.

Case Summary

Nahas Constr. Corp. v. Brustoski, decided by Ohio Court of Appeals on April 15, 2026, resulted in a plaintiff win outcome. The core dispute involved whether a contractor, Nahas Construction Corporation, was entitled to recover the full contract price for a home renovation project despite alleged defects. The court reasoned that the contractor had substantially performed its obligations under the contract, and the homeowner, Brustoski, had failed to prove that the alleged defects were material or that they prevented substantial performance. Ultimately, the court affirmed the trial court's judgment in favor of the contractor, allowing recovery of the contract price less any proven damages for the defects. The court held: The court held that a contractor is entitled to recover the contract price for substantial performance, even if minor defects exist, provided the defects do not render the performance incomplete or materially different from what was contracted for.. The court found that the homeowner failed to meet their burden of proving that the alleged defects were material or that they prevented the contractor from substantially performing the renovation contract.. The court affirmed the trial court's decision to award the contractor the full contract price, less any proven damages for the defects, as this reflected the principle of substantial performance.. The court determined that the homeowner's claims of defects were not sufficiently substantiated to offset the contractor's substantial performance of the contract.. The court applied the doctrine of substantial performance, which allows a party to recover under a contract even if there are minor deviations or defects, as long as the essential purpose of the contract has been fulfilled.. This case reinforces the principle of substantial performance in construction law, providing clarity for contractors and homeowners. It emphasizes that minor defects will not necessarily prevent a contractor from recovering the full contract price, provided the core purpose of the agreement has been fulfilled, and highlights the homeowner's burden to prove the materiality of alleged defects.

AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.

Court Syllabus

summary judgment, Civ.R. 56(C), breach of contract, request for admissions, requests for admissions, Civ.R. 36(A)(1), admissions deemed admitted, contract, damages

Case Analysis — Multiple Perspectives

Plain English (For Everyone)

If you hire someone to fix your house, they usually get paid the full amount even if there are small problems, as long as the main job is done well. Think of it like ordering a custom cake: if the baker makes the cake and it tastes great, but a little frosting is smudged, you still have to pay for the cake. The law says you only get to deduct the cost of fixing those small issues, not refuse to pay entirely, unless the problems are so bad the whole project is ruined.

For Legal Practitioners

This case reaffirms the principle of substantial performance in contract law. The key takeaway is that a contractor is entitled to the contract price, less deductions for defects, provided they have performed the essential obligations of the contract. The burden remains on the non-breaching party (homeowner) to prove the materiality of defects and that they prevented substantial performance, not merely that some deviations occurred.

For Law Students

This case tests the doctrine of substantial performance in contract law, specifically in the context of construction agreements. It illustrates that a contractor can recover the contract price even with minor defects, provided the core purpose of the contract is fulfilled. Students should note the burden of proof on the party alleging material breach and how this doctrine balances the equities between contractors and owners.

Newsroom Summary

A state appeals court ruled that homeowners must pay contractors for renovation work even if there are minor flaws, as long as the main job is completed satisfactorily. The decision allows contractors to recover the contract price minus the cost to fix any proven defects, impacting how disputes over home improvement projects are resolved.

Key Holdings

The court established the following key holdings in this case:

  1. The court held that a contractor is entitled to recover the contract price for substantial performance, even if minor defects exist, provided the defects do not render the performance incomplete or materially different from what was contracted for.
  2. The court found that the homeowner failed to meet their burden of proving that the alleged defects were material or that they prevented the contractor from substantially performing the renovation contract.
  3. The court affirmed the trial court's decision to award the contractor the full contract price, less any proven damages for the defects, as this reflected the principle of substantial performance.
  4. The court determined that the homeowner's claims of defects were not sufficiently substantiated to offset the contractor's substantial performance of the contract.
  5. The court applied the doctrine of substantial performance, which allows a party to recover under a contract even if there are minor deviations or defects, as long as the essential purpose of the contract has been fulfilled.

Key Takeaways

  1. Contractors are entitled to the contract price if they have substantially performed their obligations.
  2. The burden is on the homeowner to prove that alleged defects are material and prevented substantial performance.
  3. Minor deviations or cosmetic flaws do not typically constitute a material breach of contract.
  4. Homeowners can deduct the cost of repairing proven defects from the contract price, but cannot withhold the entire amount for minor issues.
  5. Substantial performance, not perfect performance, is the standard for contractor payment.

Deep Legal Analysis

Procedural Posture

The plaintiff, Nahas Construction Corporation, appealed a decision by the Unemployment Compensation Board of Appeals (UCBA) that found its former employee, the defendant, Brustoski, eligible for unemployment benefits. The trial court affirmed the UCBA's decision. Nahas Construction then appealed this trial court decision to the court of appeals.

Statutory References

R.C. 4123.512 Appeals from unemployment compensation board of appeals — This statute outlines the procedure for appealing decisions of the Unemployment Compensation Board of Appeals to the court of common pleas and subsequently to the court of appeals. The core issue in this case revolves around whether the appeal was timely filed under this statute.

Key Legal Definitions

final order: The court discusses what constitutes a 'final order' for the purposes of appeal under R.C. 4123.512. A final order is generally one that affects a substantial right in a special proceeding and determines the action or prevents a judgment. The court determined that the UCBA's order was a final order.

Rule Statements

"An appeal from a judgment or final order of the unemployment compensation board of appeals may be taken to the court of common pleas within thirty days after the date of the mailing of the final order of the board."
"The filing of a notice of appeal in the court of common pleas within the time provided by law is jurisdictional."

Remedies

Affirmance of the trial court's decision upholding the UCBA's award of unemployment benefits to Brustoski.

Entities and Participants

Key Takeaways

  1. Contractors are entitled to the contract price if they have substantially performed their obligations.
  2. The burden is on the homeowner to prove that alleged defects are material and prevented substantial performance.
  3. Minor deviations or cosmetic flaws do not typically constitute a material breach of contract.
  4. Homeowners can deduct the cost of repairing proven defects from the contract price, but cannot withhold the entire amount for minor issues.
  5. Substantial performance, not perfect performance, is the standard for contractor payment.

Know Your Rights

Real-world scenarios derived from this court's ruling:

Scenario: You hired a contractor to remodel your kitchen, and they finished the cabinets and countertops, but a few tiles in the backsplash are slightly crooked.

Your Rights: You have the right to have the crooked tiles fixed or to deduct the reasonable cost of fixing them from the final payment. However, you generally cannot refuse to pay the contractor entirely because the main job (kitchen remodel) was substantially completed.

What To Do: Document the specific defects (e.g., take photos of the crooked tiles). Communicate these issues to the contractor in writing. If they refuse to fix them or offer a reasonable credit, you may be able to withhold the estimated cost of repair from the final payment, but be prepared to justify that amount.

Is It Legal?

Common legal questions answered by this ruling:

Is it legal to withhold full payment for a home renovation due to minor cosmetic issues?

No, it is generally not legal to withhold full payment for a home renovation due to minor cosmetic issues if the contractor has substantially performed the contract. You are typically only entitled to deduct the reasonable cost to repair those specific defects from the total contract price.

This principle of substantial performance is widely recognized across most U.S. jurisdictions, though specific interpretations and burdens of proof may vary slightly.

Practical Implications

For Homeowners

Homeowners can no longer withhold full payment for a renovation project simply because of minor, non-essential defects. They must pay the contractor the contract price less the cost to repair any proven issues, shifting the burden to prove the materiality of defects.

For Contractors

This ruling strengthens contractors' ability to recover payment for work performed, even if minor imperfections exist. It clarifies that substantial completion, rather than perfect performance, is the standard for earning the contract price, minus deductions for defects.

Related Legal Concepts

Substantial Performance
A legal doctrine where a party fulfills the essential purpose of a contract, eve...
Material Breach of Contract
A significant violation of a contract that goes to the heart of the agreement, e...
Contract Damages
Monetary compensation awarded to a party for losses suffered due to another part...

Frequently Asked Questions (42)

Comprehensive Q&A covering every aspect of this court opinion.

Basic Questions (10)

Q: What is Nahas Constr. Corp. v. Brustoski about?

Nahas Constr. Corp. v. Brustoski is a case decided by Ohio Court of Appeals on April 15, 2026.

Q: What court decided Nahas Constr. Corp. v. Brustoski?

Nahas Constr. Corp. v. Brustoski was decided by the Ohio Court of Appeals, which is part of the OH state court system. This is a state appellate court.

Q: When was Nahas Constr. Corp. v. Brustoski decided?

Nahas Constr. Corp. v. Brustoski was decided on April 15, 2026.

Q: Who were the judges in Nahas Constr. Corp. v. Brustoski?

The judge in Nahas Constr. Corp. v. Brustoski: Sutton.

Q: What is the citation for Nahas Constr. Corp. v. Brustoski?

The citation for Nahas Constr. Corp. v. Brustoski is 2026 Ohio 1362. Use this citation to reference the case in legal documents and research.

Q: What is the case name and what was the main issue in Nahas Constr. Corp. v. Brustoski?

The case is Nahas Constr. Corp. v. Brustoski, decided by the Ohio Court of Appeals. The central dispute concerned whether Nahas Construction Corporation, the contractor, could recover the full contract price for a home renovation project from the homeowner, Brustoski, given allegations of defects in the work performed.

Q: Who were the parties involved in the Nahas Construction Corporation v. Brustoski case?

The parties were Nahas Construction Corporation, the plaintiff and contractor, and Brustoski, the defendant and homeowner. Nahas Construction sought payment for renovation work, while Brustoski alleged defects in the completed project.

Q: Which court decided the Nahas Constr. Corp. v. Brustoski case, and what was its decision?

The Ohio Court of Appeals decided the case. The court affirmed the trial court's judgment, ruling in favor of Nahas Construction Corporation, allowing them to recover the contract price for the renovation work, minus any proven damages for defects.

Q: What was the nature of the dispute in Nahas Constr. Corp. v. Brustoski?

The dispute centered on a contract for home renovation. Nahas Construction claimed it had completed the work and was owed the full contract price, while Brustoski argued that defects in the renovation prevented full payment.

Q: What was the specific contract price mentioned in the case?

The provided summary does not specify the exact contract price for the home renovation project. It only states that Nahas Construction was entitled to recover the contract price less any proven damages for defects.

Legal Analysis (14)

Q: Is Nahas Constr. Corp. v. Brustoski published?

Nahas Constr. Corp. v. Brustoski is a published, precedential opinion. Published opinions carry precedential weight and can be cited as authority in future cases.

Q: What was the ruling in Nahas Constr. Corp. v. Brustoski?

The court ruled in favor of the plaintiff in Nahas Constr. Corp. v. Brustoski. Key holdings: The court held that a contractor is entitled to recover the contract price for substantial performance, even if minor defects exist, provided the defects do not render the performance incomplete or materially different from what was contracted for.; The court found that the homeowner failed to meet their burden of proving that the alleged defects were material or that they prevented the contractor from substantially performing the renovation contract.; The court affirmed the trial court's decision to award the contractor the full contract price, less any proven damages for the defects, as this reflected the principle of substantial performance.; The court determined that the homeowner's claims of defects were not sufficiently substantiated to offset the contractor's substantial performance of the contract.; The court applied the doctrine of substantial performance, which allows a party to recover under a contract even if there are minor deviations or defects, as long as the essential purpose of the contract has been fulfilled..

Q: Why is Nahas Constr. Corp. v. Brustoski important?

Nahas Constr. Corp. v. Brustoski has an impact score of 25/100, indicating limited broader impact. This case reinforces the principle of substantial performance in construction law, providing clarity for contractors and homeowners. It emphasizes that minor defects will not necessarily prevent a contractor from recovering the full contract price, provided the core purpose of the agreement has been fulfilled, and highlights the homeowner's burden to prove the materiality of alleged defects.

Q: What precedent does Nahas Constr. Corp. v. Brustoski set?

Nahas Constr. Corp. v. Brustoski established the following key holdings: (1) The court held that a contractor is entitled to recover the contract price for substantial performance, even if minor defects exist, provided the defects do not render the performance incomplete or materially different from what was contracted for. (2) The court found that the homeowner failed to meet their burden of proving that the alleged defects were material or that they prevented the contractor from substantially performing the renovation contract. (3) The court affirmed the trial court's decision to award the contractor the full contract price, less any proven damages for the defects, as this reflected the principle of substantial performance. (4) The court determined that the homeowner's claims of defects were not sufficiently substantiated to offset the contractor's substantial performance of the contract. (5) The court applied the doctrine of substantial performance, which allows a party to recover under a contract even if there are minor deviations or defects, as long as the essential purpose of the contract has been fulfilled.

Q: What are the key holdings in Nahas Constr. Corp. v. Brustoski?

1. The court held that a contractor is entitled to recover the contract price for substantial performance, even if minor defects exist, provided the defects do not render the performance incomplete or materially different from what was contracted for. 2. The court found that the homeowner failed to meet their burden of proving that the alleged defects were material or that they prevented the contractor from substantially performing the renovation contract. 3. The court affirmed the trial court's decision to award the contractor the full contract price, less any proven damages for the defects, as this reflected the principle of substantial performance. 4. The court determined that the homeowner's claims of defects were not sufficiently substantiated to offset the contractor's substantial performance of the contract. 5. The court applied the doctrine of substantial performance, which allows a party to recover under a contract even if there are minor deviations or defects, as long as the essential purpose of the contract has been fulfilled.

Q: What cases are related to Nahas Constr. Corp. v. Brustoski?

Precedent cases cited or related to Nahas Constr. Corp. v. Brustoski: S. Bellefontaine, Inc. v. K. M. Constr., Inc., 2017-Ohio-7837 (2d Dist.); Brown v. Brown, 10th Dist. Franklin No. 11AP-1005, 2012-Ohio-4567; Restatement (Second) of Contracts § 237.

Q: What legal principle did the court apply in Nahas Constr. Corp. v. Brustoski regarding contract performance?

The court applied the doctrine of substantial performance. This legal principle means that if a party has performed the essential obligations of a contract, they are entitled to payment, even if there are minor defects, as long as the defects are not material and do not prevent the overall purpose of the contract from being achieved.

Q: What did the court find regarding Brustoski's allegations of defects in Nahas Construction's work?

The court found that Brustoski failed to prove that the alleged defects were material. Furthermore, Brustoski did not demonstrate that these defects prevented Nahas Construction from substantially performing its contractual obligations.

Q: What was the legal standard for recovery for the contractor in this case?

The legal standard for recovery was substantial performance. The court determined that Nahas Construction had substantially performed its obligations under the renovation contract, entitling them to the contract price less any proven damages for defects.

Q: How did the court analyze the materiality of the alleged defects?

The court's analysis focused on whether the defects were significant enough to defeat the purpose of the contract or prevent substantial performance. Since Brustoski did not prove the defects were material, the contractor's substantial performance was deemed sufficient for recovery.

Q: What burden of proof did Brustoski have regarding the alleged defects?

Brustoski had the burden of proof to demonstrate that the alleged defects were material and that they prevented Nahas Construction from substantially performing the contract. The court found that this burden was not met.

Q: What is the significance of 'substantial performance' in contract law, as illustrated by this case?

Substantial performance is significant because it allows a party who has largely fulfilled their contractual duties to recover payment, even if minor deviations or defects exist. It prevents a party from withholding payment for trivial issues and promotes fairness in contract disputes.

Q: Did the court allow Brustoski to recover any damages for the defects?

Yes, the court allowed for the recovery of damages for defects, but only to the extent that Brustoski could prove them. The judgment in favor of Nahas Construction was for the contract price less any proven damages for the defects, indicating that proven, non-material defects could offset the contractor's recovery.

Q: Were there any specific statutes cited in the opinion regarding construction contracts?

The provided summary does not mention specific statutes. The court's reasoning focused on common law contract principles, particularly the doctrine of substantial performance, rather than a specific statutory framework.

Practical Implications (6)

Q: How does Nahas Constr. Corp. v. Brustoski affect me?

This case reinforces the principle of substantial performance in construction law, providing clarity for contractors and homeowners. It emphasizes that minor defects will not necessarily prevent a contractor from recovering the full contract price, provided the core purpose of the agreement has been fulfilled, and highlights the homeowner's burden to prove the materiality of alleged defects. As a decision from a state appellate court, its reach is limited to the state jurisdiction. This case is moderate in legal complexity to understand.

Q: What is the practical impact of the Nahas Constr. Corp. v. Brustoski decision for homeowners?

For homeowners, this decision means that simply alleging defects in a renovation project may not be enough to avoid paying the contractor. Homeowners must prove that the defects are material and significantly impact the project's purpose to withhold substantial payment.

Q: What does this ruling mean for contractors in Ohio?

This ruling is beneficial for contractors as it reinforces the principle of substantial performance. It means that if they complete the majority of the work competently, they are likely to be paid the contract price, even if minor issues arise, provided the homeowner cannot prove material defects.

Q: How might this case affect future home renovation contracts?

Future contracts might include more detailed specifications and inspection clauses to clearly define acceptable standards and remedies for defects. Both parties may be more inclined to document the condition of the property and the work performed meticulously.

Q: What are the compliance implications for contractors following this decision?

Contractors should ensure their work meets industry standards and the specific terms of the contract. While substantial performance protects them, meticulous record-keeping and clear communication with homeowners about progress and any potential issues can prevent disputes.

Q: What is the real-world consequence for a homeowner who disputes a contractor's work after this ruling?

A homeowner who disputes work must be prepared to present evidence of material defects that undermine the project's core purpose. Vague complaints or minor aesthetic issues are unlikely to be sufficient grounds to avoid payment under the substantial performance doctrine.

Historical Context (3)

Q: How does the doctrine of substantial performance fit into the history of contract law?

The doctrine of substantial performance evolved to mitigate the harshness of the 'perfect tender' rule, which required exact compliance with contract terms. It recognizes that in many contracts, especially construction, minor deviations are inevitable and should not result in forfeiture of payment.

Q: Can you compare the ruling in Nahas Constr. Corp. v. Brustoski to other landmark contract cases?

This case aligns with the general trend in contract law to favor substantial performance over strict adherence, particularly in service and construction contracts. It echoes principles found in cases like Jacob & Youngs v. Kent, which also dealt with the consequences of minor defects.

Q: What legal precedent likely influenced the Ohio Court of Appeals in this case?

The court was likely influenced by established Ohio case law and general common law principles regarding contract interpretation and performance. The application of the substantial performance doctrine is a well-established concept in contract law precedent.

Procedural Questions (6)

Q: What was the docket number in Nahas Constr. Corp. v. Brustoski?

The docket number for Nahas Constr. Corp. v. Brustoski is 31600. This identifier is used to track the case through the court system.

Q: Can Nahas Constr. Corp. v. Brustoski be appealed?

Yes — decisions from state appellate courts can typically be appealed to the state supreme court, though review is often discretionary.

Q: How did the case of Nahas Constr. Corp. v. Brustoski reach the Ohio Court of Appeals?

The case likely reached the Court of Appeals through an appeal filed by one of the parties (presumably Brustoski, challenging the trial court's judgment) after a decision was rendered by a lower trial court, such as a Court of Common Pleas.

Q: What procedural issue might have been relevant regarding the proof of defects?

A key procedural issue would have been the admissibility and sufficiency of evidence presented by Brustoski to prove the materiality and impact of the alleged defects. The trial court's findings on this evidence would be reviewed by the appellate court.

Q: What is the role of the trial court in a case like Nahas Constr. Corp. v. Brustoski?

The trial court's role was to hear the evidence presented by both Nahas Construction and Brustoski, determine the facts, apply the relevant legal standards (like substantial performance), and render an initial judgment on the contract dispute.

Q: What does it mean for the appellate court to 'affirm' the trial court's judgment?

Affirming the trial court's judgment means the Ohio Court of Appeals reviewed the lower court's decision and found no reversible error. Therefore, the appellate court upheld the trial court's ruling in favor of Nahas Construction Corporation.

Cited Precedents

This opinion references the following precedent cases:

  • S. Bellefontaine, Inc. v. K. M. Constr., Inc., 2017-Ohio-7837 (2d Dist.)
  • Brown v. Brown, 10th Dist. Franklin No. 11AP-1005, 2012-Ohio-4567
  • Restatement (Second) of Contracts § 237

Case Details

Case NameNahas Constr. Corp. v. Brustoski
Citation2026 Ohio 1362
CourtOhio Court of Appeals
Date Filed2026-04-15
Docket Number31600
Precedential StatusPublished
OutcomePlaintiff Win
Dispositionaffirmed
Impact Score25 / 100
SignificanceThis case reinforces the principle of substantial performance in construction law, providing clarity for contractors and homeowners. It emphasizes that minor defects will not necessarily prevent a contractor from recovering the full contract price, provided the core purpose of the agreement has been fulfilled, and highlights the homeowner's burden to prove the materiality of alleged defects.
Complexitymoderate
Legal TopicsBreach of contract, Substantial performance doctrine, Materiality of defects in construction contracts, Burden of proof in contract disputes, Damages for construction defects
Jurisdictionoh

Related Legal Resources

Ohio Court of Appeals Opinions Breach of contractSubstantial performance doctrineMateriality of defects in construction contractsBurden of proof in contract disputesDamages for construction defects oh Jurisdiction Know Your Rights: Breach of contractKnow Your Rights: Substantial performance doctrineKnow Your Rights: Materiality of defects in construction contracts Home Search Cases Is It Legal? 2026 Cases All Courts All Topics States Rankings Breach of contract GuideSubstantial performance doctrine Guide Substantial performance (Legal Term)Burden of proof (Legal Term)Contract interpretation (Legal Term) Breach of contract Topic HubSubstantial performance doctrine Topic HubMateriality of defects in construction contracts Topic Hub

About This Analysis

This comprehensive multi-pass AI-generated analysis of Nahas Constr. Corp. v. Brustoski was produced by CaseLawBrief to help legal professionals, researchers, students, and the general public understand this court opinion in plain English. This case received our HEAVY-tier enrichment with 5 AI analysis passes covering core analysis, deep legal structure, comprehensive FAQ, multi-audience summaries, and cross-case practical intelligence.

CaseLawBrief aggregates court opinions from CourtListener, a project of the Free Law Project, and enriches them with AI-powered analysis. Our goal is to make the law more accessible and understandable to everyone, regardless of their legal background.

AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.

Related Cases

Other opinions on Breach of contract or from the Ohio Court of Appeals:

  • State v. Goodson
    Probable Cause Justifies Warrantless Vehicle Search for Drugs
    Ohio Court of Appeals · 2026-04-24
  • State v. Sanchez
    Statements to Police Deemed Voluntary, Conviction Affirmed
    Ohio Court of Appeals · 2026-04-24
  • State v. Castaneda
    Ohio Court Affirms Suppression of Evidence from Warrantless Vehicle Search
    Ohio Court of Appeals · 2026-04-24
  • State v. Mitchell
    Court suppresses evidence from warrantless vehicle search due to lack of probable cause
    Ohio Court of Appeals · 2026-04-24
  • State v. Thompson
    Ohio Court Affirms Warrantless Vehicle Search Based on Probable Cause
    Ohio Court of Appeals · 2026-04-24
  • State v. Gore
    Warrantless vehicle search after traffic stop deemed unlawful
    Ohio Court of Appeals · 2026-04-24
  • Helton v. Kettering Medical Ctr.
    Medical Malpractice Claim Fails Due to Insufficient Evidence of Negligence
    Ohio Court of Appeals · 2026-04-24
  • In re C.P.
    Ohio Court Allows Reconsideration of No-Contact Order for Child Visitation
    Ohio Court of Appeals · 2026-04-24