Florida Rising, Inc. v. Florida Public Service Commission
Headline: PSC Approval of FPL Settlement Upheld
Citation:
Brief at a Glance
The court upheld the state's decision allowing Florida Power & Light to charge customers for costs incurred on a canceled nuclear plant, finding the decision was rational.
- Courts grant significant deference to the Florida Public Service Commission's decisions regarding utility rate settlements.
- To overturn a PSC decision, challengers must prove it lacks a rational basis or is arbitrary and capricious.
- Utilities can potentially recover costs for canceled projects if the PSC finds a reasonable basis for the expenses.
Case Summary
Florida Rising, Inc. v. Florida Public Service Commission, decided by Florida Supreme Court on July 17, 2025, resulted in a defendant win outcome. The core dispute centered on whether the Florida Public Service Commission (PSC) properly approved a settlement agreement between Florida Power & Light (FPL) and the PSC staff, which allowed FPL to recover costs associated with a canceled nuclear power plant. Florida Rising, Inc. (FRI) argued that the PSC's approval was arbitrary and capricious because it did not adequately consider the public interest and the reasonableness of the costs. The court affirmed the PSC's decision, finding that the PSC had a rational basis for approving the settlement and that FRI failed to demonstrate that the PSC's actions were unlawful. The court held: The court held that the Florida Public Service Commission (PSC) acted within its statutory authority when it approved the settlement agreement between Florida Power & Light (FPL) and PSC staff regarding the recovery of costs for a canceled nuclear power plant.. The court found that the PSC's decision to approve the settlement was not arbitrary or capricious, as it was supported by a rational basis and considered the relevant factors, including the reasonableness of the costs and the public interest.. The court held that Florida Rising, Inc. (FRI) failed to meet its burden of proving that the PSC's approval of the settlement was unlawful or constituted an abuse of discretion.. The court affirmed the PSC's determination that the settlement agreement was a reasonable resolution of the complex issues involved in the cost recovery for the canceled nuclear project.. This decision reinforces the deference courts typically give to administrative agencies like the Florida Public Service Commission when reviewing their decisions. It highlights the high burden of proof required for parties challenging agency actions under the arbitrary and capricious standard, particularly in complex regulatory matters involving utility rate-making and cost recovery.
AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.
Case Analysis — Multiple Perspectives
Plain English (For Everyone)
Imagine your electric company planned a big, expensive project, like building a new power plant, but then canceled it. This case is about whether the company can still charge you for the money they already spent on the canceled project. The court said that in this situation, the state's Public Service Commission made a reasonable decision to allow the company to recover some of those costs, and the consumer group challenging it didn't prove the decision was unfair.
For Legal Practitioners
The appellate court affirmed the PSC's approval of a settlement allowing FPL to recover costs for a canceled nuclear plant, finding a rational basis for the decision. The key takeaway is that challenges to PSC settlements require demonstrating a lack of rational basis or arbitrary and capricious action, a high bar for intervenors like Florida Rising. Practitioners should note the deference given to the PSC's administrative expertise in evaluating settlement reasonableness and cost recovery.
For Law Students
This case tests the standard of review for administrative agency decisions, specifically the Florida Public Service Commission's approval of a settlement agreement. The court applied the 'rational basis' test, affirming the PSC's decision to allow FPL to recover costs for a canceled nuclear plant. This illustrates the deference courts give to agency findings when they are not arbitrary or capricious, a crucial concept in administrative law and judicial review of agency actions.
Newsroom Summary
The Florida Supreme Court has sided with Florida Power & Light, allowing the utility to recover costs from a canceled nuclear power plant. Consumer advocates argued the decision was unfair, but the court found the Public Service Commission's approval had a rational basis, impacting future utility rate cases.
Key Holdings
The court established the following key holdings in this case:
- The court held that the Florida Public Service Commission (PSC) acted within its statutory authority when it approved the settlement agreement between Florida Power & Light (FPL) and PSC staff regarding the recovery of costs for a canceled nuclear power plant.
- The court found that the PSC's decision to approve the settlement was not arbitrary or capricious, as it was supported by a rational basis and considered the relevant factors, including the reasonableness of the costs and the public interest.
- The court held that Florida Rising, Inc. (FRI) failed to meet its burden of proving that the PSC's approval of the settlement was unlawful or constituted an abuse of discretion.
- The court affirmed the PSC's determination that the settlement agreement was a reasonable resolution of the complex issues involved in the cost recovery for the canceled nuclear project.
Key Takeaways
- Courts grant significant deference to the Florida Public Service Commission's decisions regarding utility rate settlements.
- To overturn a PSC decision, challengers must prove it lacks a rational basis or is arbitrary and capricious.
- Utilities can potentially recover costs for canceled projects if the PSC finds a reasonable basis for the expenses.
- Consumer groups must present strong evidence to successfully challenge PSC approvals of utility cost recovery.
- The 'rational basis' standard is a high bar for intervenors seeking to invalidate administrative agency actions.
Deep Legal Analysis
Constitutional Issues
Whether the Florida Public Service Commission exceeded its statutory authority in approving the settlement agreement.Whether the settlement agreement was arbitrary, capricious, or otherwise unlawful.
Rule Statements
"The PSC has broad statutory authority to regulate public utilities, including the power to approve or disapprove rate increase petitions and to enter into settlements."
"An agency action is arbitrary or capricious if it is unreasonable, irrational, or lacking in a rational basis."
"The PSC's approval of a settlement agreement is presumed valid and will not be overturned unless it is found to be arbitrary, capricious, or otherwise unlawful."
Entities and Participants
Key Takeaways
- Courts grant significant deference to the Florida Public Service Commission's decisions regarding utility rate settlements.
- To overturn a PSC decision, challengers must prove it lacks a rational basis or is arbitrary and capricious.
- Utilities can potentially recover costs for canceled projects if the PSC finds a reasonable basis for the expenses.
- Consumer groups must present strong evidence to successfully challenge PSC approvals of utility cost recovery.
- The 'rational basis' standard is a high bar for intervenors seeking to invalidate administrative agency actions.
Know Your Rights
Real-world scenarios derived from this court's ruling:
Scenario: You receive your monthly electricity bill and notice an increase, and you learn it's partly to cover costs for a power plant that was never completed. You are part of a consumer advocacy group that believes this is unfair.
Your Rights: You have the right to have your utility costs reviewed by a state regulatory body like the Public Service Commission. You also have the right to challenge decisions you believe are unreasonable or unfair, and to appeal those decisions to higher courts.
What To Do: If you believe your utility company is unfairly charging you for uncompleted projects, join or support consumer advocacy groups that monitor utility rates and challenge questionable charges before the Public Service Commission. If a decision is made, these groups can pursue legal avenues to appeal.
Is It Legal?
Common legal questions answered by this ruling:
Is it legal for my electric company to charge me for a power plant that was never built?
It depends. If the utility company followed the proper regulatory process and the state's Public Service Commission found a rational basis for allowing the recovery of costs associated with the canceled project (like planning or initial construction expenses), then it can be legal. However, if the process was flawed or the decision was arbitrary, it may not be.
This ruling is specific to Florida law and the Florida Public Service Commission's authority.
Practical Implications
For Utility Ratepayers
Ratepayers in Florida may see their electricity bills include charges related to costs incurred by utility companies for canceled projects, as the court has affirmed the PSC's ability to approve such cost recovery. This means consumers may bear some of the financial burden for projects that do not ultimately provide service.
For Utility Companies
Utility companies in Florida have greater assurance that the Public Service Commission can approve the recovery of costs associated with canceled major projects, provided they can demonstrate a rational basis for the expenses. This can reduce financial risk for utilities undertaking large-scale infrastructure planning.
For Consumer Advocacy Groups
Consumer advocacy groups face a higher burden of proof when challenging PSC decisions on cost recovery, as demonstrated by this ruling. They must show a clear lack of rational basis or that the PSC acted arbitrarily, rather than simply disagreeing with the outcome.
Related Legal Concepts
A legal standard used by courts to review administrative agency actions, requiri... Rational Basis Review
The lowest level of judicial scrutiny, requiring that a law or government action... Administrative Law
The body of law that governs the activities of administrative agencies of govern... Deference to Agencies
The principle that courts should give weight and respect to the interpretations ... Cost Recovery
The process by which a company is allowed to recoup expenses it has incurred, of...
Frequently Asked Questions (41)
Comprehensive Q&A covering every aspect of this court opinion.
Basic Questions (9)
Q: What is Florida Rising, Inc. v. Florida Public Service Commission about?
Florida Rising, Inc. v. Florida Public Service Commission is a case decided by Florida Supreme Court on July 17, 2025.
Q: What court decided Florida Rising, Inc. v. Florida Public Service Commission?
Florida Rising, Inc. v. Florida Public Service Commission was decided by the Florida Supreme Court, which is part of the FL state court system. This is a state supreme court.
Q: When was Florida Rising, Inc. v. Florida Public Service Commission decided?
Florida Rising, Inc. v. Florida Public Service Commission was decided on July 17, 2025.
Q: What is the citation for Florida Rising, Inc. v. Florida Public Service Commission?
The citation for Florida Rising, Inc. v. Florida Public Service Commission is . Use this citation to reference the case in legal documents and research.
Q: What is the case name and who are the main parties involved in Florida Rising, Inc. v. Florida Public Service Commission?
The case is Florida Rising, Inc. v. Florida Public Service Commission. The main parties are Florida Rising, Inc. (FRI), an organization advocating for consumer interests, and the Florida Public Service Commission (PSC), the state agency responsible for regulating utilities. The dispute also involved Florida Power & Light (FPL), the utility company whose costs were at issue.
Q: What was the central issue that Florida Rising, Inc. (FRI) raised against the Florida Public Service Commission (PSC)?
FRI's central argument was that the PSC acted arbitrarily and capriciously when it approved a settlement agreement between FPL and the PSC staff. FRI contended that this approval did not sufficiently consider the public interest and the reasonableness of the costs FPL sought to recover for a canceled nuclear power plant.
Q: What specific action by the Florida Public Service Commission (PSC) did Florida Rising, Inc. (FRI) challenge?
FRI challenged the PSC's approval of a settlement agreement. This agreement allowed Florida Power & Light (FPL) to recover costs associated with a nuclear power plant that was ultimately canceled, a decision FRI believed was not adequately scrutinized for public benefit and cost reasonableness.
Q: What was the outcome of the Florida Rising, Inc. v. Florida Public Service Commission case?
The court affirmed the Florida Public Service Commission's (PSC) decision. The court found that the PSC had a rational basis for approving the settlement agreement between FPL and the PSC staff, and that Florida Rising, Inc. (FRI) did not successfully demonstrate that the PSC's actions were unlawful.
Q: When was the decision in Florida Rising, Inc. v. Florida Public Service Commission rendered?
The provided summary does not specify the exact date the court rendered its decision in Florida Rising, Inc. v. Florida Public Service Commission. However, it indicates the court affirmed the Florida Public Service Commission's approval of a settlement agreement concerning Florida Power & Light's canceled nuclear plant costs.
Legal Analysis (15)
Q: Is Florida Rising, Inc. v. Florida Public Service Commission published?
Florida Rising, Inc. v. Florida Public Service Commission is a published, precedential opinion. Published opinions carry precedential weight and can be cited as authority in future cases.
Q: What was the ruling in Florida Rising, Inc. v. Florida Public Service Commission?
The court ruled in favor of the defendant in Florida Rising, Inc. v. Florida Public Service Commission. Key holdings: The court held that the Florida Public Service Commission (PSC) acted within its statutory authority when it approved the settlement agreement between Florida Power & Light (FPL) and PSC staff regarding the recovery of costs for a canceled nuclear power plant.; The court found that the PSC's decision to approve the settlement was not arbitrary or capricious, as it was supported by a rational basis and considered the relevant factors, including the reasonableness of the costs and the public interest.; The court held that Florida Rising, Inc. (FRI) failed to meet its burden of proving that the PSC's approval of the settlement was unlawful or constituted an abuse of discretion.; The court affirmed the PSC's determination that the settlement agreement was a reasonable resolution of the complex issues involved in the cost recovery for the canceled nuclear project..
Q: Why is Florida Rising, Inc. v. Florida Public Service Commission important?
Florida Rising, Inc. v. Florida Public Service Commission has an impact score of 25/100, indicating limited broader impact. This decision reinforces the deference courts typically give to administrative agencies like the Florida Public Service Commission when reviewing their decisions. It highlights the high burden of proof required for parties challenging agency actions under the arbitrary and capricious standard, particularly in complex regulatory matters involving utility rate-making and cost recovery.
Q: What precedent does Florida Rising, Inc. v. Florida Public Service Commission set?
Florida Rising, Inc. v. Florida Public Service Commission established the following key holdings: (1) The court held that the Florida Public Service Commission (PSC) acted within its statutory authority when it approved the settlement agreement between Florida Power & Light (FPL) and PSC staff regarding the recovery of costs for a canceled nuclear power plant. (2) The court found that the PSC's decision to approve the settlement was not arbitrary or capricious, as it was supported by a rational basis and considered the relevant factors, including the reasonableness of the costs and the public interest. (3) The court held that Florida Rising, Inc. (FRI) failed to meet its burden of proving that the PSC's approval of the settlement was unlawful or constituted an abuse of discretion. (4) The court affirmed the PSC's determination that the settlement agreement was a reasonable resolution of the complex issues involved in the cost recovery for the canceled nuclear project.
Q: What are the key holdings in Florida Rising, Inc. v. Florida Public Service Commission?
1. The court held that the Florida Public Service Commission (PSC) acted within its statutory authority when it approved the settlement agreement between Florida Power & Light (FPL) and PSC staff regarding the recovery of costs for a canceled nuclear power plant. 2. The court found that the PSC's decision to approve the settlement was not arbitrary or capricious, as it was supported by a rational basis and considered the relevant factors, including the reasonableness of the costs and the public interest. 3. The court held that Florida Rising, Inc. (FRI) failed to meet its burden of proving that the PSC's approval of the settlement was unlawful or constituted an abuse of discretion. 4. The court affirmed the PSC's determination that the settlement agreement was a reasonable resolution of the complex issues involved in the cost recovery for the canceled nuclear project.
Q: What cases are related to Florida Rising, Inc. v. Florida Public Service Commission?
Precedent cases cited or related to Florida Rising, Inc. v. Florida Public Service Commission: Florida Power & Light Co. v. Fla. Pub. Serv. Comm'n, 435 So. 2d 411 (Fla. 1983); Agrico Chemical Co. v. Dep't of Envtl. Regulation, 404 So. 2d 1164 (Fla. 1st DCA 1981).
Q: What legal standard did the court apply when reviewing the Florida Public Service Commission's (PSC) decision?
The court applied a standard of review to determine if the PSC's decision had a rational basis. This means the court looked for a logical connection between the facts found by the PSC and the choice made, and whether the PSC's actions were not arbitrary or capricious.
Q: What did Florida Rising, Inc. (FRI) need to prove to overturn the PSC's decision regarding the FPL settlement?
FRI needed to demonstrate that the Florida Public Service Commission's (PSC) approval of the settlement agreement was unlawful. Specifically, they had to show that the PSC's actions were arbitrary and capricious, meaning they lacked a rational basis or were not supported by the evidence presented.
Q: Did the court find that the Florida Public Service Commission (PSC) adequately considered the public interest in approving the FPL settlement?
Yes, the court found that the PSC had a rational basis for approving the settlement agreement. This implies the court determined the PSC's consideration of the public interest, in conjunction with the reasonableness of costs for FPL's canceled nuclear plant, was sufficient to support its decision.
Q: What was the core legal argument Florida Rising, Inc. (FRI) made regarding the reasonableness of costs?
FRI argued that the Florida Public Service Commission (PSC) failed to adequately consider the reasonableness of the costs Florida Power & Light (FPL) sought to recover for its canceled nuclear power plant. They contended that the PSC's approval of the settlement agreement did not sufficiently scrutinize these costs from a public interest perspective.
Q: What does it mean for a regulatory agency's decision to be 'arbitrary and capricious' in the context of this case?
A decision is considered 'arbitrary and capricious' if it lacks a rational basis, meaning there is no logical connection between the facts found and the choice made by the agency. In this case, FRI argued the PSC's approval of the FPL settlement was arbitrary and capricious because it allegedly ignored the public interest and cost reasonableness.
Q: Did the court's ruling in this case set a new precedent for utility cost recovery in Florida?
The provided summary indicates the court affirmed the PSC's existing decision-making process, finding a rational basis for approving the settlement. It does not suggest the ruling established a new legal precedent but rather reinforced the existing standard of review for PSC actions concerning utility cost recovery.
Q: What is the role of the Florida Public Service Commission (PSC) in utility rate cases?
The Florida Public Service Commission (PSC) is the state agency responsible for regulating investor-owned utility companies, including setting rates and approving major expenditures. In this case, the PSC's role was to review and approve a settlement agreement that determined whether Florida Power & Light could recover costs for a canceled nuclear power plant.
Q: How does the concept of 'rational basis' apply to the PSC's approval of the FPL settlement?
The court used the 'rational basis' test to uphold the PSC's decision. This means the court looked to see if there was a logical and reasonable justification for the PSC's approval of the settlement agreement, even if other outcomes might have been possible. The court found such a basis existed.
Q: What burden of proof did Florida Rising, Inc. (FRI) have in challenging the PSC's decision?
Florida Rising, Inc. (FRI) had the burden of proving that the Florida Public Service Commission's (PSC) decision to approve the settlement agreement was unlawful. This meant demonstrating that the PSC's actions lacked a rational basis and were therefore arbitrary and capricious.
Practical Implications (6)
Q: How does Florida Rising, Inc. v. Florida Public Service Commission affect me?
This decision reinforces the deference courts typically give to administrative agencies like the Florida Public Service Commission when reviewing their decisions. It highlights the high burden of proof required for parties challenging agency actions under the arbitrary and capricious standard, particularly in complex regulatory matters involving utility rate-making and cost recovery. As a decision from a state supreme court, its reach is limited to the state jurisdiction. This case is moderate in legal complexity to understand.
Q: What are the practical implications of this ruling for Florida consumers?
The ruling means that Florida Power & Light (FPL) was allowed to recover costs associated with its canceled nuclear power plant, as approved by the PSC settlement. For consumers, this likely translates to these costs being factored into their utility rates, as the court affirmed the PSC's decision-making process.
Q: How does this case affect how Florida utilities can recover costs for canceled projects?
This case affirms that the Florida Public Service Commission (PSC) has the authority to approve settlement agreements allowing utilities like FPL to recover costs for canceled projects, provided the PSC's decision has a rational basis. It suggests that challenging such approvals requires demonstrating the PSC acted arbitrarily or capriciously.
Q: Who is most directly impacted by the court's decision in Florida Rising, Inc. v. Florida Public Service Commission?
The Florida Public Service Commission (PSC) and Florida Power & Light (FPL) are directly impacted, as their decision to approve the settlement and the subsequent recovery of costs were upheld. Florida consumers are also impacted, as the costs associated with the canceled nuclear plant will likely be reflected in their utility bills.
Q: What does this ruling mean for advocacy groups like Florida Rising, Inc. (FRI)?
For advocacy groups like FRI, this ruling signifies a challenge in overturning regulatory approvals. They must present strong evidence to prove that agencies like the PSC acted without a rational basis or in an arbitrary and capricious manner when approving utility settlements, rather than simply disagreeing with the outcome.
Q: Are there any compliance changes for Florida utilities following this decision?
The ruling itself does not mandate new compliance changes for Florida utilities. Instead, it reinforces the existing regulatory framework and the standard of review applied to the Florida Public Service Commission's (PSC) decisions regarding cost recovery for projects, like FPL's canceled nuclear plant.
Historical Context (3)
Q: How does this case fit into the broader history of utility regulation in Florida?
This case is part of a long history of regulatory oversight of utilities in Florida, where the PSC balances the need for reliable service and infrastructure investment by utilities with the protection of consumer interests. The dispute over cost recovery for canceled projects, like nuclear plants, has been a recurring theme in utility regulation.
Q: What legal doctrines or principles were at play in this case?
Key legal doctrines included administrative law principles governing judicial review of agency actions, specifically the 'arbitrary and capricious' standard and the 'rational basis' test. The case also involved principles of utility regulation and contract law related to settlement agreements.
Q: Can this case be compared to other landmark cases involving utility cost recovery or regulatory agency review?
While the summary doesn't name specific comparable cases, it operates within the established framework of administrative law where courts review agency decisions for reasonableness. Landmark cases in administrative law often define the scope of judicial deference to agencies like the PSC, setting the stage for how challenges like FRI's are evaluated.
Procedural Questions (5)
Q: What was the docket number in Florida Rising, Inc. v. Florida Public Service Commission?
The docket number for Florida Rising, Inc. v. Florida Public Service Commission is SC2024-0485. This identifier is used to track the case through the court system.
Q: Can Florida Rising, Inc. v. Florida Public Service Commission be appealed?
Generally no within the state system — a state supreme court is the court of last resort for state law issues. However, if a federal constitutional question is involved, a party may petition the U.S. Supreme Court for review.
Q: How did the case reach the appellate court that issued this decision?
Florida Rising, Inc. (FRI) likely appealed the Florida Public Service Commission's (PSC) decision to approve the settlement agreement to a state appellate court. The court's role was to review the PSC's administrative decision for legal error or lack of a rational basis, as mandated by Florida law.
Q: What type of procedural ruling did the court make in affirming the PSC's decision?
The court made an affirmance, meaning it upheld the lower decision (the PSC's approval of the settlement). This procedural outcome indicates the appellate court found no reversible error in the PSC's administrative process or its ultimate decision regarding Florida Power & Light's cost recovery.
Q: Were there any specific evidentiary issues raised by Florida Rising, Inc. (FRI) regarding the FPL settlement?
The summary focuses on FRI's argument that the PSC's approval was arbitrary and capricious due to inadequate consideration of the public interest and cost reasonableness. It does not detail specific evidentiary disputes, but implies FRI believed the evidence presented did not sufficiently support the PSC's finding of reasonableness.
Cited Precedents
This opinion references the following precedent cases:
- Florida Power & Light Co. v. Fla. Pub. Serv. Comm'n, 435 So. 2d 411 (Fla. 1983)
- Agrico Chemical Co. v. Dep't of Envtl. Regulation, 404 So. 2d 1164 (Fla. 1st DCA 1981)
Case Details
| Case Name | Florida Rising, Inc. v. Florida Public Service Commission |
| Citation | |
| Court | Florida Supreme Court |
| Date Filed | 2025-07-17 |
| Docket Number | SC2024-0485 |
| Precedential Status | Published |
| Outcome | Defendant Win |
| Disposition | affirmed |
| Impact Score | 25 / 100 |
| Significance | This decision reinforces the deference courts typically give to administrative agencies like the Florida Public Service Commission when reviewing their decisions. It highlights the high burden of proof required for parties challenging agency actions under the arbitrary and capricious standard, particularly in complex regulatory matters involving utility rate-making and cost recovery. |
| Complexity | moderate |
| Legal Topics | Administrative Law, Public Utility Regulation, Rate Making, Agency Adjudication, Arbitrary and Capricious Standard of Review, Florida Public Service Commission Authority |
| Jurisdiction | fl |
Related Legal Resources
About This Analysis
This comprehensive multi-pass AI-generated analysis of Florida Rising, Inc. v. Florida Public Service Commission was produced by CaseLawBrief to help legal professionals, researchers, students, and the general public understand this court opinion in plain English. This case received our HEAVY-tier enrichment with 5 AI analysis passes covering core analysis, deep legal structure, comprehensive FAQ, multi-audience summaries, and cross-case practical intelligence.
CaseLawBrief aggregates court opinions from CourtListener, a project of the Free Law Project, and enriches them with AI-powered analysis. Our goal is to make the law more accessible and understandable to everyone, regardless of their legal background.
AI-generated summary for informational purposes only. Not legal advice. May contain errors. Consult a licensed attorney for legal advice.
Related Cases
Other opinions on Administrative Law or from the Florida Supreme Court:
-
James Ernest Hitchcock v. State of Florida
Florida court upholds conviction, admitting prior 'bad acts' evidenceFlorida Supreme Court · 2026-04-23
-
Armando Arce v. Chief Judge Timothy D. Osterhaus
Judicial immunity shields judge from civil suit over alleged due process violationsFlorida Supreme Court · 2026-04-23
-
In Re: Amendments to Rules Regulating the Florida Bar - Substance Use Terminology
Florida Supreme Court Approves Amendments to Substance Use Terminology RulesFlorida Supreme Court · 2026-04-16
-
Joseph Zieler v. State of Florida
Florida Supreme Court Affirms Dismissal of Plaintiff's Constitutional ClaimsFlorida Supreme Court · 2026-04-16
-
Chadwick Willacy v. State of Florida & Chadwick Willacy v. State of Florida
Appellate Court Upholds Vehicle Search and ConvictionsFlorida Supreme Court · 2026-04-15
-
In Re: Amendments to Florida Rules of Appellate Procedure
Florida Supreme Court Approves Amendments to Appellate RulesFlorida Supreme Court · 2026-04-09
-
In Re: Amendments to Florida Rules of Appellate Procedure
Florida Supreme Court · 2026-03-19
-
In Re: Amendments to Rules Regulating the Florida Bar - Professionalism Expectations
Florida Supreme Court · 2026-03-19